Fig. 7: Transport lugs / lashing points on the machine
1
Transport lugs
2
Lashing points
Only the existing transport lugs (1) should be used to transport / lift the machine.
Only the existing lashing points (2) should be used to lash the machine.
Only lifting equipment that is functional, flawless and suitable for the load to be
transported should be used.
The following steps must be observed when transporting / lashing the machine:
1.
Turn off the engine, turn the disconnect switch and pull out.
2.
When lifting the machine with a hoist, only attach the lifting equipment to the
transport lugs (1).
3.
When lashing the machine with tensioning elements, only use the indicated
lashing points (2).
4
Pre-tension the lashing / tensioning elements and ensure that they are in the
correct position and that the load is distributed correctly.
5.
Before unloading the machine, take care to ensure that there are no
obstacles on the ground in front of the loading ramps, as this could cause a
collision. When unloading multiple machines, move them far enough away
from the loading zone.