Commissioning
If a capacitive value is displayed, or if the "G" symbol is flashing, the phase allocation of
the current and voltage measurement is incorrect. In the Commissioning programming
menu, the phase allocation can be changed using the functions Rot. field U and Rot.
field I (provided that there is no generator in operation at the time).
The first switching operation may take up to 10 seconds. The stages are switched in set
switching times (switching interval) until compensation occurs. The displayed cos phi
must increase to at least the set target cos phi