KPS SERIES
Installation
M-UK-KPS--06
11/02/03 Page 39 of 138
KALTENBACH
3.4
Setup
Order of setting up:
-
Set up the punching-shearing machine at the right height and level in a straight
line
-
Set up the marking unit at the right height and level in a straight line. (option)
-
Set up the input roller conveyor with rail in a straight line and level at the right
height
-
Set up the column punching machine at the right height and level in a straight
line with the input roller conveyor
-
Set up the sawing machine (option) at the right height and level in a straight
line with the input roller conveyor
-
Set up the output table way in a straight line and level at the right height
-
Place the operation desk and fixed it to the floor by means of 4 stay bolts.
-
Place the safety fences and/or safety light guards
-
Fix and connect the electrical cable work according to the electrical diagrams
which are delivered with the machine.
-
Fix and connect the pneumatic tubes according to the diagrams which are
delivered with the machine.
3.4.1
Setup the safety fences and safety light guards
For the protection against moving parts a safety protection is provided.
The safety protection can consists of safety fences, safety light guards and/or
emergency switch buttons.
The safety fences and light guards must be fixed to the floor by means of stay bolts.
The position of the safety protections must be in accordance with the construction
Layout drawing which is delivered prior to the shipment of the machine
Содержание KPS 501
Страница 1: ...MANUAL KPS 515 Serial No 2008 01 14564...
Страница 2: ......
Страница 6: ...KPS SERIES Contents M UK KPS 06 11 02 03 Page 6 of 138 KALTENBACH 7 Appendix 138...
Страница 97: ...KPS SERIES Maintenance M UK KPS 06 11 02 03 Page 97 of 138 KALTENBACH Flange punch 8X 2X each year four shots...
Страница 103: ...KPS SERIES Maintenance M UK KPS 06 11 02 03 Page 103 of 138 KALTENBACH Angle shear DC No grease points...
Страница 105: ...KPS SERIES Maintenance M UK KPS 06 11 02 03 Page 105 of 138 KALTENBACH Drill Unit 1x 1x each year four shots...
Страница 106: ...KPS SERIES Maintenance M UK KPS 06 11 02 03 Page 106 of 138 KALTENBACH 1x 2x 2x each year four shots...
Страница 135: ...KPS SERIES Technical Documentation M UK KPS 06 11 02 03 Page 135 of 138 KALTENBACH 6 4 Pneumatic drawings...
Страница 136: ......
Страница 137: ...KPS SERIES Technical Documentation M UK KPS 06 11 02 03 Page 136 of 138 KALTENBACH 6 5 Hydraulic drawings...
Страница 142: ...KPS SERIES Technical Documentation M UK KPS 06 11 02 03 Page 137 of 138 KALTENBACH 6 6 Electric drawings...
Страница 263: ......
Страница 264: ......
Страница 265: ......
Страница 266: ......
Страница 267: ......