Part 1, Mounting the Switch into a 4 Post Rack

The QFX5200-32C and QFX5200-32C-L can only be mounted in a four-post rack configuration. To mount the device in

a 19-inch rack:

1. Attach the ESD grounding strap to your bare wrist and to a site ESD point

WARNING:

Ensure that you understand how to prevent ESD damage by proper use of an ESD

grounding strap.

2. Place the rack in its permanent location, allowing adequate clearance for airflow and maintenance, and secure it to the

building structure.

WARNING:

If you are mounting multiple units in the rack, mount the heaviest unit at the bottom

and mount the others from bottom to top in order of decreasing weight. The switch weighs

approximately 23.5 lb (10.66 kg). Installing the QFX5200-32C in a rack or cabinet requires two people

to lift the switch and secure it to the rack.

3. Align the holes in the side mounting-rail with the holes on the side of the chassis as shown in

Figure 1

.

Figure 1: Align Side Mounting-Rail with Chassis Holes

4. Attach the side mounting-rail to the switch using six mounting screws.

5. Repeat steps

3

and

4

on the opposite side of the chassis.

6. Have one person grasp both sides of the switch, lift it, and position it in the rack so that the front bracket is aligned

with the rack holes.

7. Have a second person secure the front of the switch to the rack using four mounting screws (and cage nuts and washers

if your rack requires them.) Tighten the screws

3

Содержание QFX5200-32C

Страница 1: ...and control plane are driven by the 1 8 Ghz quad core Intel CPU with 16 GB of memory and two 32 GB solid state drives SSD for storage The QFX5200 32C and QFX5200 32C L comes standard with redundant fans and redundant power supplies Switches can be ordered with either ports to FRUs or FRUs to ports airflow The QFX5200 32C is available with AC or DC power supplies the QFX5200 32C L is available only...

Страница 2: ...0 10A L or equivalent two 10 32 x 0 25 screws with 10 split lock washers to secure the grounding lug to the grounding lug bracket protective earthing terminal Provided Two power cords with plugs appropriate to your geographical location Provided RJ 45 cable and RJ 45 to DB 9 serial port adapter Not Provided A Management host such as a laptop or PC with an Ethernet port Provided An Ethernet cable w...

Страница 3: ...m bottom to top in order of decreasing weight The switch weighs approximately 23 5 lb 10 66 kg Installing the QFX5200 32C in a rack or cabinet requires two people to lift the switch and secure it to the rack 3 Align the holes in the side mounting rail with the holes on the side of the chassis as shown in Figure 1 Figure 1 Align Side Mounting Rail with Chassis Holes 4 Attach the side mounting rail ...

Страница 4: ...g the blades to the rack Use the four mounting screws and cage nuts and washers if your rack requires them to attach each blade to the rack Tighten the screws Figure 3 Slide Mounting Blade into Mounting Rail g004478 9 Ensure that the switch chassis is level by verifying that all the screws on the front of the rack are aligned with the screws at the back of the rack 4 ...

Страница 5: ...g terminal on the protective earthing terminal bracket 4 Secure the grounding lug to the protective earthing terminal with two nuts 5 Dress the grounding cable and ensure that it does not touch or block access to other device components and that it does not drape where people could trip over it Connect Power to the Switch The QFX5200 32C and QFX5200 32C L ships with two factory installed power sup...

Страница 6: ...s on the console server or PC Baud Rate 9600 Flow Control None Data 8 Parity None Stop Bits 1 DCD State Disregard To connect and configure the switch from the console 1 Connect the console port to a laptop or PC using the supplied RJ 45 cable and RJ 45 to DB 9 adapter The console CON port is located on the management panel of the switch 2 Log in as root There is no password If the software booted ...

Страница 7: ...and prefix length for the switch management interface For QFX5200 32C systems edit root set interfaces em0 unit 0 family inet address address prefix length For QFX5200 32C L systems edit root set interfaces re0 mgmt 0 unit 0 family inet address address prefix length CAUTION Although the CLI permits you to configure two management Ethernet interfaces within the same subnet only one interface is usa...

Страница 8: ...y or death Permit only trained and qualified personnel to install or replace switch components Perform only the procedures described in this quick start and the QFX5200 documentation Other services must be performed only by authorized service personnel Before installing the switch read the planning instructions in the QFX5200 documentation to make sure that the site meets power environmental and c...

Страница 9: ...to track the returned material at the factory and to return repaired or new components to the customer as needed For more information about return and repair policies see the customer support Web page at https www juniper net support guidelines html For product problems or technical support issues contact the Juniper Networks Technical Assistance Center JTAC by using the Case Manager link at https...