InStALLIng

COntRACtOR: ___________________________
StARt-UP 

tECHnICIAn/ 

COmPAnY: _______________________________

StARt-UP DAtE :  _________________________

CHILLER mODEL #: _______________________
SERIAL #: ______________________________

CHECkIng tHE SYStEm  

PRIOR tO InItIAL StARt (nO POWER)

Unit Checks

 1.  Inspect the unit for shipping or installation dam-

age.

 2.  Assure that all piping has been completed.

 3.  Visually check for refrigerant piping leaks.

 4.  Open suction line ball valve, discharge line ball 

valve, and liquid line valve for each system.

 5.  The compressor oil level should be maintained so 

that an oil level is visible in the sight glass. The 

oil level can only be tested when the compressor 

is running in stabilized conditions, guaranteeing 

that there is no liquid refrigerant in the lower shell 

of the compressor. In this case, the oil should be 

between 1/4 and 3/4 in the sight glass. At shut-

down, the oil level can fall to the bottom limit of 

the oil sight glass.

 6.  Assure water pumps are on. Check and adjust 

water pump flow rate and pressure drop across 

the cooler.  Verify flow switch operation.

Excessive flow may cause catastrophic 

damage to the evaporator.

EqUIPmEnt StARtUP CHECkLISt

 

7.  Check the control panel to ensure it is free of  

foreign material (wires, metal chips, etc.).

 8.  Visually inspect wiring (power and control). Wir-

ing MUST meet N.E.C. and local codes. 

9.  Check tightness of power wiring inside the power 

panel on both sides of the motor contactors and 

overloads.

10. Check for proper size fuses in main and control 

circuits, and verify overload setting corresponds 

with RLA and FLA values.  

Refer to Electrical 

Tables in the IOM (150.66-NM4) or unit name-

plate.

11. Assure 120VAC Control Power to TB1 has 15  

amp minimum capacity. 

12. Be certain all water temp sensors are inserted   

completely in their respective wells and are coated 

with heat conductive compound.

13. Assure that evaporator TXV bulbs are strapped 

onto the suction lines at 4 or 8 o’clock positions 

or suction temp. sensors if EEVs are installed.

COmPRESSOR HEAtERS  

(POWER On – 24 HOURS PRIOR tO StARt)

1.  Apply  120VAC  and  verify  its  value  between 

terminals 5 and 2 of TB1. The voltage should be 

/- 10%. 

      Power must be applied 24 hours prior to 

      start-up. 
      Each heater should draw approximately 0.5-1A.

PAnEL CHECkS  

(POWER On  –  BOtH UnIt SWItCHES OFF)

 1.  Apply 3-phase power and verify its value. Volt-

age imbalance should be no more than 2% of the 

average voltage.

 2.  Apply 120VAC and verify its value on the terminal 

block in the Power Panel. Make the measurement 

between terminals 5 and 2 of TB1. The voltage 

should be /- 10%.

 3.  Program/verify the Cooling Setpoints, Program 

Setpoints, and unit Options. 

Record the values in 

Table 1.