Note:
Refer to the
N2 Communications
Bus Technical Bulletin (LIT-636018)
for the
N2 bus EOL termination rules. Refer to
the
MS/TP Communications Bus Technical
Bulletin (LIT-12011034
) for the FC bus EOL
termination rules.
3. If the field controller is a terminating device on
the N2 or FC Bus, set the EOL switch to ON. If
the field controller is not a terminating device
on the bus, set the EOL switch to OFF.
Note:
When the EOL switch is set to ON,
the LED light on the face of the controller
is illuminated.
Commissioning
Use the following procedure to commission the
VMA18 controller:
1. Download the control application to the VMA
controller using the CCT. Refer to the Controller
Tool
Help (LIT-12011147)
.
2. Commission the VAV Box. Refer to the
Controller
Tool Help (LIT-12011147)
.
3. Perform airflow balancing on the VAV box.
Refer to the
VAV Balancing Tool Technical Bulletin
(LIT-12011087)
.
4. Perform commissioning checkout procedures.
Refer to the
Controller Tool Help (LIT-12011147)
.
CCT connects to the VMA through a laptop
computer using any one of the following connection
options: the MAP Gateway, BTCVT, the Wireless
ZigBee USB Dongle, or the wired BACnet
®
Ethernet
to MS/TP Router. These connection options require
additional hardware listed in Table 9.
For more detailed N2 VMA controller commissioning
information, refer to the
N2 VMA Application Note
(LIT-12011829).
Note:
• The MAP Gateway serves as a replacement
for the BTCVT, which is no longer available
for purchase, but continues to be supported
on select controllers.
• CCT 10.3 auto-detects when BTCVT can be
used or not, based on the controller model
and the corresponding CCT Release mode.
•
- BTCVT can be used with controllers
that contain CCT Release mode 10.2 or
earlier firmware.
Metasys
controllers from Release 9.0 or
earlier support BTCVT.
- BTCVT cannot be used with controllers
that contain CCT Release mode 10.4.
Metasys
Release 10.0 controllers
use CCT Release mode
10.4, therefore BTCVT is not
supported with these controllers.
VMA1826/1832 VAV Controller Installation Guide