Congratulations on the purchase of your Jayline wood fi re.
Please read this installation and operation manual carefully.
The installation of this fi re must comply with the Installation Standard
AS/NZS 2918:2001 as well as any additional local requirements.
Please ensure you have all relevant permits prior to installation.
Keep this booklet as a reference guide.
INSTALLATION OF YOUR JAYLINE WOOD FIRE
Jayline recommends you use a suitably qualifi ed installation technician to install your fi re. Your dealer
or heating specialist will be able to help with recommendations as well as advise on permits/consents
required for the installation in your area.
Please follow carefully all dimensions and recommendations provided on the individual specifi cation
sheet for your model of heater as these dimensions comply with the required New Zealand standard
(AS/NZS 2918:2001).
As safety and emissions performance can be aff ected by altering the appliance, no modifi cations are
allowed without the written permission from the manufacturer.
PRE-INSTALLATION
Prior to installing your Jayline Insert into a fi replace cavity, it is important that certain clearances and
other requirements are complied with as detailed below:
FIREPLACE CAVITY
* The chimney must be swept.
* Check for cracks and overall condition. If repairs are necessary, they must be carried out by a
suitably qualifi ed technician.
* Check the cavity dimensions to ensure the insert will fi t. It is usually necessary to remove the bricks
from the lower fi replace cavity.
* The base of the fi replace on which the Jayline Insert will rest must be level. If not, it should be
leveled using mortar.
* If a timber or combustible mantle shelf exists above the fi replace opening, it should be a minimum
distance above the top of the fl oor protector. The minimum distance is 1175mm. If less than the
minimum specifi ed, a defl ector or heat shield will be required to be under the mantle shelf.