Note
When selecting the mounting means that the maximum load on the awning is
132 N/m². In addition, you will be taken into account the weight of the awning,
which is ca. 7 kg/m².
3.8.3. Laying electric cables (if motor drive was ordered)
●
Drill out grommet for electrical conduit. Power to the motor drive should be prepared in accordance
with the relevant provisions.
3.8.4. Fix the pergola awning frame
Note
The main task of the pergola awning PRO is the protection from sunlight. There is also
the possibility of extra protection from the rain. The effectiveness of the removal of
water depends on the awning fabric, inclination angle of the pergola and used
accessories like gutter system and water blockade on sides.
●
Attach the right pilar to the prepared substrate.
●
Place the right guide (1) from the wall in the mounting bracket and lock screw (2)
●
Embed guide holder (3) on the head of the column (4) and secure with screws (5).
●
Possible slight readjustment of the guide bracket (3) can be made loosening slightly screw (6) and
after adjustment tighten again.
Right side of the awning
●
The same way like for right guide install next (left) guide (7). This operation is performed together
with the rear face of the beam (8) in
the sockets of the head (4).
●
This action consists in inserting and studs mounted on the front ends of the beam (8)
socket head (4) and secure the Allen screws (9) located in the head (4).