10
IQ Power BPS
5201249 Rev. D
Figure 9. Jumper Position at J3 for Remote Control Operation
Initial Considerations
Installation starts with mounting of the static neutralizing bar. Static bars are
typically installed just ahead of where problems due to static are occurring. The
power supply is installed in a convenient location within reach of the static bar
high voltage cable (standard length 3m [10 ft]) and visible to the machine operator.
Control station (where used) may be installed at any convenient location and
connected to the system using the modular low voltage cable.
Mounting the Static Neutralizing Bar
CAUTION – Fire Hazard
Do not install or operate static neutralizing bar in close proximity to any
flammable liquids or solvents.