Intergraph Salient Fibre Channel Скачать руководство пользователя страница 8

6

NOTE

Alignment screws are located in the upper left corner of each power supply bay, and in the
upper left corner of the slot 2.  You only need to remove the alignment screws above each
power supply bay at this time.

CAUTION

Be very careful with the power supplies, as they are heavy and the connecting pins can be
easily bent.

5.  Install the first power supply (CPWS17900) in slot four; hold down the black tab to

make sure the component clicks into place.

CAUTION

Make sure the label on the power supply faces the left of the chassis rear, or the power
supply will break when you install it.  This is the same label that would be on the top of the
power supply in a rack-mount unit.

6.  Using the same method described in the previous step, install the second power supply

(CPWS179) into slot 1.

7.  Reinsert the two alignment screws and washers that you removed in step 2.

8.  Remove the key that is taped to the operator panel (CINFE48), and install the panel in

the column 1 of slot 3, making sure that the “This Side Up” label on the operator panel
faces the left of the chassis rear; this label would be on the top in a rack-mount unit.  Set
the key aside for now.

9.  Insert the I/O module (CINFE49) in the middle column of slot 3.  Again, make sure that

the “This Side Up” label faces the left of the chassis rear.

10.  Place the smaller blanking plate (CGEN575) over the last column (3) in slot 3.

11.  Remove the alignment screws and washers above slot 2, and place the final blanking

plate (CGEN574) over slot 2.

Populating the Fibre Channel Storage System Drive Bays

The following instructions show you how to install all of the drives in the proper order.
There are eight drives (CDSK238) and four dummy carriers (CGEN576) in a typical setup.
To open the drive front, you will push the indentation on the plastic cover.  This indentation
should be on the top of each drive.

To install the Fibre Channel storage system drives:

1.  Turn the storage system around so that you are looking at the front of the unit (refer to

the illustration in “Unpacking and Orienting the Fibre Channel Chassis” if necessary).

2.  Press the indentation on a drive to open its door, and install this first drive in the bottom

right column of slot 4.  Push the drive all the way in until the face of the drive is flush
with the trim on the tower cover, then press the indentation until it clicks shut.  Again,
the indentation on the drive should be on the top.

3.  Continue to install the remaining drives in the same fashion, working your way to the

top of the right column, then starting over at the bottom (slot 4) of the middle column.

Содержание Salient Fibre Channel

Страница 1: ...Salient Fibre Channel Storage System Tower Assembly Instructions August 1998 DHA024800...

Страница 2: ...ocument is subject to change without notice and should not be considered a commitment by Intergraph Computer Systems Intergraph Computer Systems shall not be liable for technical or editorial errors i...

Страница 3: ...chassis and make sure you have all the components and then determine which end of the chassis will be the top of the tower unit To unpack and orient the chassis 1 Open the box containing the Fibre Cha...

Страница 4: ...cover which is protected by a layer of protective wrap CAUTION All of the tower kit components are contained within the tower kit cover To ensure that you do not scratch the surface of the tower cover...

Страница 5: ...on the foot 3 Use two M6 pan head screws and washers to attach the front of the foot to the bottom front of the chassis the pan head screws and their washers are the larger of the two types of screws...

Страница 6: ...the rear bracket screws you inserted in step 7 so that they are fully countersunk 10 Turn the unit upside down again and use six M5 countersunk screws to secure the cover to the unit 11 Turn the unit...

Страница 7: ...omponents 1 Remove the protective covering from each of the storage system components 2 Check the power supplies and verify that the voltage switch is set to the correct voltage either 115V or 220V fo...

Страница 8: ...in the middle column of slot 3 Again make sure that the This Side Up label faces the left of the chassis rear 10 Place the smaller blanking plate CGEN575 over the last column 3 in slot 3 11 Remove the...

Страница 9: ...nnel storage system NOTE See the StudioZ GT for SOFTIMAGE DS System Guide for information on this workstation Workstation Requirements StudioZ GT1 base unit Q Logic adapter card CINFE50 Q Logic driver...

Страница 10: ...drives and you can purchase four additional drives for each storage system To add an additional Fibre Channel storage system 1 Connect the HSSDC end of the Fibre Channel cable MCBL337 to the Fibre Cha...

Страница 11: ...he cable thumbscrews 6 Power up your StudioZ GT1 workstation and turn the keys in each Fibre Channel I O module from Service to Run to power up the Fibre Channel storage systems See SS 1200 FCAL Rack...