2. INSTALLATION
To get detailed information about the installation process, please visit:
https://intellimeter.ca/pages/downloads#videos
: Intellimeter i-meter®MF6 Installation &
Troubleshooting and/or Intellimeter i meter®MF3 Installation & Troubleshooting.
Verify the number of breakers is the same as the number of meters assigned for that panel board.
Follow the installation drawings. Group the assigned modules to the identified panel board.
Referring to the diagram below, CTs can be embedded in the distribution panel. If the customer has
supplied a special compartment for the meter with their electrical panel, Intellimeter will install the
meter and have the SPE-1000 field evaluation completed. Otherwise, the meter will be installed in
an external enclosure to be mounted near the electrical panel for ease of servicing.
Install the modules into their appropriate position.
Voltage connectors are fixed to the meter PCB. Contractor has to wire to the meter board and use
the wire terminals (spade connectors) provided.
Terminate the voltage reference chain to the designated, 15Amp breaker and ensure the proper
phasing retained as per drawings.
Install the communication connectors to the meter modules and dress the wires they are protected
from damage during feeder and branch circuit installation.
MF series can be provided with a pulse
output cable upon request.
Communication cable is to be terminated to a junction box outside of the panel board by the
electrical contractor.
Review general information and wiring diagram.
Carefully read all the WARNING signs and notes.
Check meter serial number and other information on the meter.
All meter modules are assigned within the panel board and are identified with respect to position,
or section of breakers.
A label on the top of each unit indicates meter assignment. Follow the installation drawings that are
supplied with the units.
Do not leave the secondary CT open when current is flowing through the primary circuit. This
applies to instrument CTs as ICI milliamp CTs are self-protected.
Contact ICI if there has been a change made to the layout or if the assigned drawings do not match
the actual distribution panel layout.