The following subsections outline sample product regulations requirements for a
typical power supply. Actual requirements will depend on the design, product end use,
target geography, and other variables. Consult your company’s Product Safety and
Regulations department or an accredited third-party certification agency for more
details.
9.1
North America – REQUIRED
The power supply must be certified by an NRTL (Nationally Recognized Testing
Laboratory) for use in the USA and Canada under the following conditions:
•
The power supply UL report “Conditions of Acceptability” shall meet in the intended
application of the power supply in the end product.
•
The supply must be recognized for use in Information Technology Equipment
including Electrical Business Equipment per UL 60950-1 First Edition. The
certification must include external enclosure testing for the AC receptacle side of
the power supply.
•
The supply must have a full complement of tests conducted as part of the
certification, such as input current, leakage current, hi-pot, temperature, energy
discharge test, transformer output characterization test (open-circuit voltage, short-
circuit performance), and abnormal testing (to include stalled-fan tests and voltage-
select–switch mismatch).
•
The enclosure must meet fire enclosure mechanical test requirements per clauses
2.9.1 and 4.2 of the above-mentioned standard.
•
Production hi-pot testing must be included as a part of the certification and
indicated as such in the certification report.
•
There must not be unusual or difficult conditions of acceptability such as mandatory
additional cooling or power de-rating. The insulation system shall not have
temperatures exceeding their rating when tested in the end product.
•
The certification mark shall be marked on each power supply.
•
The power supply must be evaluated for operator-accessible secondary outputs
(reinforced insulation) that meet the requirements for SELV.
•
The proper polarity between the AC input receptacle and any printed wiring boards
connections must be maintained (that is, brown=line, blue=neutral, and
green=earth/chassis).
•
The fan shall be protected by a guard to prevent contact by a finger in compliance
with UL accessibility requirements.
9.2
International – REQUIRED
The vendor must provide a complete CB certificate and test report to IEC 60950-1.
The CB report must include ALL CB member country national deviations as appropriate
for the target market. All evaluations and certifications must be for reinforced
insulation between primary and secondary circuits.
Содержание ATX 3.0
Страница 69: ...LFX12V Specific Guidelines 2 0 336521 69 Figure 12 2 Mechanical Details...
Страница 70: ...LFX12V Specific Guidelines 2 0 70 336521 Figure 12 3 PSU Slot Feature Detail...
Страница 71: ...LFX12V Specific Guidelines 2 0 336521 71 Figure 12 4 Recommended Chassis Tab Feature...
Страница 77: ...SFX12V Specific Guidelines 4 0 336521 77 Figure 14 3 Top Mount Fan Profile Mechanical Outline...
Страница 82: ...SFX12V Specific Guidelines 4 0 82 336521 Figure 14 10 PS3 Mechanical Outline...
Страница 84: ...TFX12V Specific Guidelines 3 0 84 336521 Figure 15 2 Dimensions and Recommended Feature Placements not to scale...
Страница 87: ...TFX12V Specific Guidelines 3 0 336521 87 Figure 15 6 Suggested Mounting Tab chassis feature...