background image

Installation

The boiler must be installed on a horizontal work 

surface with sufficient strength to support its 

weight. 
Locate in an area where there is adequate space 

to use the boiler safely (e.g. free from risk of 

congestion and tripping hazards).  

Connection to Mains Water Supply:

Connect the WRAS approved water filling hose 

(3/4”BSP) to the inlet connection point on the 

back of the boiler and the other end to the mains 

water supply, via an accessible isolating tap with 

a ¾”BSP thread.

IMPORTANT: If micro-bore pipe is used 

instead of the inlet hose supplied, the size 

must be minimum OD 3/8”(10mm).

The water supply must have a pressure not 

exceeding 7bar (96psi), and no lower than 2bar 

(28psi) NOTE: If your water pressure exceeds 

7bar, fit a suitable pressure reduction valve.

We regret that Instanta cannot be held 
responsible for any machine malfunctions if 
the water pressure exceeds that stated. If in 
doubt, consult your water supply company

Electrical Connection:

The boiler must be Earthed.

All 3.0KW models:

Your machine is supplied 

with a standard 13amp bonded plug with a 

13amp fuse.  

 

All 6.0KW models:

Your machine is supplied with a 1.5mtr cord  

(3-core @ 2.5mm). Wire to at least a 30amp 

supply via an all-pole disconnection isolator 

switch (easily accessible for safety). Only a 

qualified electrician should undertake this work.     

Overflow:

The drip-tray has a limited capacity and is 

designed to handle small spillages and drips. 

Wherever possible, we strongly recommend that 

it is connected to a permanent waste.
We have provided two overflow outlet/

connection points to choose from; 

1). FRONT via drip-tray

If this option is used for the overflow, we 

can supply a 15mm fitting kit (Pt. No: DTK2) 

available from Instanta Spares Department 

(01704 502905).

2). REAR via outlet at back of machine

If rear overflow option is preferred, the front 

overflow-outlet (see diagram below), must be 

blocked off using the tapered–rubber blanking 

bung provided. Pipework should then be 

provided between the back of the machine 

[1/2”bsp – 15mm], and a suitable waste/drain. 

NOTE

: An air gap must be provided within 

300mm of the connection point. Failure to 

provide an air gap within this distance could 

cause an air lock which could stop the water 

discharging in the event of an overflow.

 

3

Model

Width

Depth

Height

Tap 

Clearance

Power 

Rating

Weight 

(empty)

Weight  

(full) 

Water Inlet 

Pressure

mm

Mm

Mm

mm

kW

KG

KG

Bar

CPF2100

260

555

610

200

3.0

15.3

29.1

2 to 7

CPF4100-3

360

555

610

200

3.0

17.5

39.0

2 to 7

CPF4100-6

360

555

610

200

6.0

17.8

39.3

2 to 7

CPF6100

440

555

610

200

6.0

21.4

53.0

2 to 7

High-tap units:

 

 

 

 

 

 

 

 

CPF210

260

555

705

304

3.0

16.3

30.1

2 to 7

CPF310

260

555

705

304

6.0

16.8

30.6

2 to 7

CPF510

360

555

705

304

3.0

18.0

39.5

2 to 7

CPF520-3

360

555

705

304

3.0

18.5

40.0

2 to 7

CPF520-6

360

555

705

304

6.0

18.8

40.3

2 to 7

Technical Specification

Содержание CPF210

Страница 1: ...PF210 CPF310 CPF510 CPF520 3 CPF520 6 Auto Fill Catering Water Boiler with Integrated Multi Filter Installation and User Instructions The Professional s Choice INSTANTA LIMITED Canning Road Southport...

Страница 2: ...NING 9 MAINTENANCE SPARES SERVICE INFORMATION 9 SERVICE WARNINGS FAULT DIAGNOSTICS 9 10 SERVICE TECHNICAL SUPPORT 11 GUARANTEE 11 Introduction Dear Customer Thank you for purchasing this Instanta prod...

Страница 3: ...Electrical Electronic Equipment The crossed out wheelie bin symbol on this product means that discarded electrical and electronic products should not be mixed with general waste Disposing of the prod...

Страница 4: ...ke this work Overflow The drip tray has a limited capacity and is designed to handle small spillages and drips Wherever possible we strongly recommend that it is connected to a permanent waste We have...

Страница 5: ...NOT READY HEATING When the correct temperature has been reached the display will change from Red to White and will simply read READY The boiler will then continue in a heat fill cycle until the tank...

Страница 6: ...sures that water is always to the highest standard whilst delivering lower maintenance costs and improved energy efficiency Quick and easy to change the new filter reduces sediment chlorine taste odou...

Страница 7: ...of the new filter and push the two together until it clicks firmly in place 7 Remove protective cap from the top of the new cartridge and ensure the two rubber seals are in place 8 Insert new cartrid...

Страница 8: ...set the monitor between 11 000 to 14 000 litres whereas locations with particularly hard water may choose to set between 5 000 to 7 000 litres To adjust filter life monitor optional Replace the filte...

Страница 9: ...elect There are three options to choose ALL set ON and OFF times once and they apply to the full 7 day week ON set the ON and OFF times separately for each day of the week OFF Default the timer is dis...

Страница 10: ...re using the boiler again Replace evaporation plates tank lid and outer lid Draw off tap The draw off tap components are subject to wear tear We strongly recommend that the tap is inspected periodical...

Страница 11: ...10 To reset boiler safety controls Safety Caution Isolate boiler from power supply before removing any outer panels or attempting any reset...

Страница 12: ...g exclusions Problems caused by hard water and lime scale We regret that we cannot be held responsible for problems caused by hard water Dripping Taps These components are subject to wear and tear but...