Installation Checklist
Complete this checklist once the unit is installed to
verify that all recommended procedures have been
accomplished before starting the system. Do not
operate the system until all items covered by this
checklist are complete.
Inspect unit location for proper required service
clearances.
Inspect unit location for proper free air clearances.
Inspect unit location for secure, level mounting
position.
Remove coil protection boards on microchannel
units.
Refrigerant Piping
Properly sized/constructed liquid and suction lines
connected to stubs at both the indoor and outdoor
units?
Insulated the entire suction line?
Insulated portions of liquid line exposed to
extremes in temperature?
Performed initial leak test?
Evacuated each refrigerant circuit to 500 microns?
Charged each circuit with proper amount of R-
410A?
Electrical Wiring
Provided unit power wiring (with disconnect) to
proper terminals in the unit control section?
Installed system indoor thermostat?
Installed system low voltage interconnecting wiring
to proper terminals of outdoor unit, indoor unit and
system thermostat?