Infiltrator tanks are compatible with the following products for buoyancy 

control:

•  Tie-down  straps: high-tensile-strength, 10,000 lb (4,500 kg) minimum 

capacity, nylon or polyester, with corrosion-resistant hardware.

 •  Concrete deadmen anchors: concrete-filled plastic half pipe, precast 

parking bumper, precast traffic barrier, or precast block.

 •  Helical  anchors: Chance™ No-Wrench Screw Anchors with minimum  

6-inch (150 mm) diameter, Class 7 or equal.

• Mid-Seam Concrete Collar: cast-in-place concrete (minimum 3,000 psi 

compressive strength at 28 days and minimum 6% air entrainment).

Tie-Down Straps

Straps are commercially available in varying 

lengths and with assorted hardware and 

tightening options. Nylon or polyester 

strapping with minimum 10,000 lb (4,500 kg) 

capacity is required for buoyancy control use 

with Infiltrator tanks. Place straps over the tank at specified locations only 

(see Figure 5). Tighten straps snugly with a ratchet or turnbuckle system to 

remove all slack and slightly pre-load the system. All connections, fittings, 

and hardware must be corrosion resistant or coated with epoxy or other 

corrosion-resistant materials to inhibit deterioration in the subsurface 

environment. Consider encapsulating such components in heat-shrink 

tubing or applying a corrosion-resistant coating prior to burial.

Concrete Deadmen Anchors

Recommended concrete deadmen anchors include filled plastic half pipe, 

precast parking bumpers and traffic barriers, and precast blocks. The 

weight of the deadmen anchors combined with the weight of soil above 

them provides buoyancy control when properly secured. Deadmen anchors 

are placed at the bottom of the tank excavation on opposite sides of the 

tank. The deadmen anchors are fastened to each other with tie-down 

straps placed over the tank at the locations specified for each tank model 

(see Figure 5).

Concrete-filled Plastic Half Pipe

Use Schedule 40 PVC plastic pipe with a minimum 

inside diameter of 15 inches (375 mm) or HDPE 

corrugated pipe with a minimum inside diameter of 

18 inches (450 mm) cut in half lengthwise. Fill with 

concrete having a minimum unit weight of 145 lbs/ft

3

 

(2.32 metric  tons/m

3

) reinforced with three equally 

spaced 40-grade, 

1/2-inch (13 mm) diameter steel bars. Weight is 61 

lbs/ft (91 kg/m) minimum.

Concrete Parking Bumper

Use commercially available steel-reinforced 

parking bumpers with typical dimensions of 12 

inches wide by 6 inches high (300 mm x 150 mm). 

Weight is 58 lbs/foot (86 kg/m) minimum.

Concrete Traffic Barrier

Use commercially available steel-reinforced concrete traffic barrier or 

equivalent. Typical dimensions include a 

24-inch-wide base tapering to a 6-inch-

wide top, with a height of approximately  

32 inches (600 mm x 150 mm x 800 mm). 

Weight is 390 lbs/foot (580 kg/m) minimum.

Precast Blocks

Concrete precasters can fabricate blocks 

of various dimensions and weights. Blocks 

are often an affordable option if they satisfy 

the minimum weight requirements for use 

as buoyancy control (see Table 2 and the 

Supplemental Force section of Step 2 for 

more information).

Helical Anchors

Chance™ No-Wrench Screw Anchors with a 

6-inch (150 mm) diameter flight, Class 7, or 

equal. These anchors rely on the shear strength 

of the soil combined with the weight of the 

soil above the anchor flight to provide holding 

strength. Proper installation is to 4 feet (1.2 m) 

below the bottom of the tank excavation and to 

within 5° of alignment with the strap alignment. 

Determine the proper locations for anchor 

installation to ensure that tie-down straps will 

be aligned properly for each tank model (see 

Step 3: Implementation), and follow the anchor 

manufacturer installation instructions.

Concrete Collar

A ballast may be constructed along the mid-

height seam of the tank using cast-in-place concrete (minimum 3,000 

psi compressive strength at 28 days and minimum 6% air entrainment). 

Concrete shall be cast in contact with the exterior surface of the tank to 

allow interlock with sidewall ribs and the mid-height flange. Reinforcing 

steel is not required, but may be added if desired.

Step 3 – Implementation

Effective buoyancy control of Infiltrator tanks requires careful preparation, 

thorough excavation, precise placement, secure strapping and proper 

backfilling, as described and illustrated below.

Excavation Requirements

It is recommended that the excavation width provide a minimum of 36 

inches (900 mm) clearance beyond the tank on all sides when utilizing 

buoyancy control. This will allow sufficient space within the excavation to 

place anchoring equipment and fasten strapping. The excavation should 

provide a minimum 48-inch (1,200 mm) clearance beyond the tank when 

using Chance™ No-Wrench Screw Anchors to allow for room to properly 

install the screw anchors. The actual excavation size shall be determined by 

the installer. Refer to Infiltrator IM-Series Tank Installation Instructions for 

additional excavation procedures.

Concrete-filled Half Pipe Construction

Concrete-filled half pipe shall be supported with soil or other stabilizing 

means below the pipe haunches prior to concrete placement.  The 

stabilization shall prevent the pipe from rolling during placement and curing 

of the concrete.  Concrete shall be allowed to cure for a minimum of one 

day prior to tank backfilling.

Placement of Deadmen and Anchors

Concrete deadman anchors are to be installed at the bottom of the tank 

excavation, parallel to the long axis of the tank (see Figure 3). 

Figure 3: Plan View

The deadmen should be placed close to, but not touching, the tank on both 

sides of the tank to allow the placement of backfill between the deadman 

anchor and tank sidewall (see Figure 4).

18 in

[450mm]

12 in

[300 mm]

6 in

[150 mm]

24 in

[600 mm]

32 in

[800 mm]

Quick4 Plus Equalizer 36 LP

Typical working torque:

¾” Rod 400 ft. lbs. (542 N

m)

1” Rod 1,000 ft. lbs. (1,356 N

m) 

1¼” Rod 2,300 ft. lbs. (3,118 N

m) 

15 in [375 mm] to

18 in [450 mm]

Steel Rebar

18 in

[450mm]

12 in

[300 mm]

6 in

[150 mm]

24 in

[600 mm]

32 in

[800 mm]

Quick4 Plus Equalizer 36 LP

STRAPPING

DEADMAN

ANCHOR

(TYPICAL)

STRAP

WIDTH

6" (150 mm)

MIN EXTENSION

6" (150 mm)

MIN EXTENSION

Contact Infiltrator Water Technologies’ Technical Services Department for assistance at 1-800-221-4436.

Содержание IM -Series

Страница 1: ...gh elevation of the main water table The vertical position of the tank must account for both the seasonal high groundwater table and any existing or future perched water table condition Verify that the subsurface water elevation will not exceed the height of the outlet pipe saddle of the tank as shown in Figure 1 and described in Table 1 Table 1 Instructions 1 In the left hand column of Table 1 lo...

Страница 2: ... outside the tank and above the tank bottom and corresponding soil cover conditions All Infiltrator strapping and fastening recommendations apply for custom designed buoyancy control methods Contact Infiltrator s Technical Services Department with any questions regarding supplemental force requirements Table 2 Buoyancy Control Method Selection Tank Model Parameter I Water height above tank bottom ...

Страница 3: ...requirements for use as buoyancy control see Table 2 and the Supplemental Force section of Step 2 for more information Helical Anchors Chance No Wrench Screw Anchors with a 6 inch 150 mm diameter flight Class 7 or equal These anchors rely on the shear strength of the soil combined with the weight of the soil above the anchor flight to provide holding strength Proper installation is to 4 feet 1 2 m...

Страница 4: ...uoyancy control methods described herein are recommendations only consult a professional engineer for customized designs if desired Parts and Supplies The parts and supplies necessary are to be purchased separately from the tank All parts and supplies are either commercially available or available through Infiltrator s network of tank distributors Some parts may require fabrication on site using c...

Отзывы: