background image

7

Concord CXS  -  

Installation & Servicing

Particular reference should be made to BS. 6644: Section 2;
Subsection 10 and Guidance note PM5 "Automatically controlled
steam and hot water boilers" published by the Health and Safety
Executive.

The  information and guidance given below is not intended to override
any requirements of either of the above publications or the
requirements of the local authority, gas or water undertakings.

Other British Standards applicable are BS.5422 & BS.6700.

The information provided is based on the following assumptions:

1.

An independent open vent/safety pipe connection is made to
the redundant boiler flow tapping or is positioned immediately
after the system flow pipe connection to the header, as shown.

2.

An independent cold feed/expansion pipe connection is made
to the redundant boiler return tapping. Cold feed/expansion pipe
connections made to the pumped system return will result in an
increase in the static head requirement, caused by the additional
resistance of the distributor tube. Surging may also increase.

3.

The maximum flow rate through the boiler is based on a
temperature difference of 11°C at full boiler output and the
circulating pump is positioned in the flow to the system.

4.

The boiler is at the highest point of circulation in the system.
Systems designed to rise above the boiler flow tappings will
automatically require a minimum static head higher than that
shown.

5.

The position of the open vent/safety pipe above the expansion
cistern water level is given as a guide only. The final position will
depend upon the particular characteristics of the system.
Pumping over of water into the expansion cistern must be
avoided.

GENERAL

Note A.

This minimum height must be increased, if
necessary, to comply with the minimum head
required by the pump manufacturer in order to
avoid cavitation.

Note B.

This diagram does not show safety valves, water
flow switches, etc., necessary for the safe
operation of the system.

PUMP POSITIONS

Whenever practically possible the circulating pump(s) should be
positioned so that it pressurises the system being served.  The
vertical distance between the pump(s) and any cold feed and
expansion cistern MUST comply with the pump manufacturers
requirements in order to avoid cavitation. These requirements
override the information given in Frame 3 if the static head
required for the pump(s) exceeds that required for the boiler.

MINIMUM FLOW OF WATER - Refer to Table 5

The system design must provide for an adequate flow rate
through the boiler at all times when the boiler is firing. The
minimum flow rate should correspond to a temperature

difference across the boiler flow and return of 35

o

C (63

o

F),

assessed at catalogue rating.

WATER TREATMENT FOR HOT WATER AND
HEATING BOILERS

There is a basic need to treat the water contained in all heating
and indirect water systems, particularly open vented systems. It is
assumed, incorrectly, that because boilers are operating in
conjunction with what is apparently a closed circuit an open vented
system will not, under normal circumstances, allow  damage or
loss of efficiency due to hardness salts and  corrosion once the
initial charge of water has been heated up a few times.

1mm of lime reduces the heat transfer from metal to water by
10%.

In practice the deposition of these salts is liable to cause noises
from the boiler body or even premature boiler failure.  Corrosion
and the formation of  black iron oxide sludge will ultimately result
in premature radiator failure.

Open vented systems are not completely sealed from the
atmosphere if  proper venting and expansion of system water is to
be achieved.  The same tank is used to fill the system with water
and it is through the cold feed pipe that system water  expands
into the tank when the boiler passes heat into the system.
Conversely, when the system cools, water previously expelled is
drawn back from the tank into the system together with a quantity
of dissolved oxygen.

Table 5 - Flow rates for fully pumped systems

Boiler

Minimum flow rates for a

temperature difference of 35 

o

C (63 

o

F)

l/s

g.p.m.

CXS 40

0.28

3.7

CXS 50

0.34

4.5

CXS 60

0.41

5.4

CXS 70

0.48

6.3

CXS 80

0.55

7.3

CXS 90

0.62

8.2

CXS 100

0.68

9

CXS 110

0.75

9.9

CXS 120

0.82

10.9

3  OPEN VENTED SYSTEMS - Minimum static head requirements

Содержание Concord CXS 40

Страница 1: ...tallers guide to commercial central heating boilers I N S TA L L AT I O N I D E A L I D E A L I D E A L I D E A L I D E A L M A N U A L T H E T H E T H E T H E T H E S E R V I C I N G Concord CXS 40 1...

Страница 2: ...cord CXS Installation Servicing CAUTION To avoid the possibility of injury during the installation servicing or cleaning of this appliance care should be taken when handling edges of sheet steel compo...

Страница 3: ...to ensure that the law is complied with The Concord CXS 40 120 range of boilers has been tested and certified by British Gas to prEN656 for use with Natural gas only Multiple boiler installations The...

Страница 4: ...7 Nett kW 28 4 33 8 40 6 47 5 54 4 61 4 67 6 74 0 81 0 Btu hr x 1000 97 0 115 3 138 5 162 5 185 6 209 5 231 7 252 5 276 4 Boiler Input Gross kW 52 5 62 5 75 1 87 93 100 7 113 5 125 0 137 4 149 8 Btu...

Страница 5: ...The mains voltage supply is via a terminal plug in connection at the control box OPTION KITS Remote Indication Kit This kit gives the facility of remote indication of boiler status Pressure Gauge Kit...

Страница 6: ...163 0 167 213 in 2 3 4 3 1 8 3 1 8 4 5 8 4 5 8 6 1 2 6 1 2 6 5 8 8 3 8 Table 4 POSITION OF BOILER Minimum clearances required from walls or other fixed objects to allow for the free access of combusti...

Страница 7: ...sitioned so that it pressurises the system being served The vertical distance between the pump s and any cold feed and expansion cistern MUST comply with the pump manufacturers requirements in order t...

Страница 8: ...ot Water Boilers 60kW to 2MW BS 6880 Pt1 3 Water Supply CP342 2 Centralised Hot Water Supply Model Water Bye laws Manufacturers notes must not be taken in any way as overriding statutory obligations T...

Страница 9: ...oilers and Air Heaters and the Third Edition of the 1956 Clean Air Act Memorandum should be strictly observed where applicable The chimney design should avoid the formation of excessive quantities of...

Страница 10: ...nout cover 2 Collector hood 3 Middle section 4 Section alignment rings O rings 5 End section 6 Gas cock 7 Drain cock 8 NOx duct 9 Front plate 10 Burner manifold assy 11 Base plate 12 Combustion chambe...

Страница 11: ...the front cross member on the packaging base 7 Remove the gas cock by unscrewing the union and screw in the handling bars into the 2 front tappings Protect the exposed inlet gas union from ingress of...

Страница 12: ...ther lower rear connection using the gasket and M10 x 25mm screws and washers provided 3 Temporarily screw the 2 handling bars 2 pipe into the top tappings and manoeuvre the boiler into position 4 Com...

Страница 13: ...2 Table 2 gives details of the inlet connection size and the minimum working pressures INSTALLATION INSTALLATION 12 CASING ASSEMBLY 1 Unpack the control box from its carton and release the temperatur...

Страница 14: ...through the cable clips as shown Ensure the phial is correctly seated in the correct pocket opposite side to the flow connection Refer to Frame 9 Secure with the split pin provided 8 Route the temper...

Страница 15: ...box is shown in Frame 15 Wiring should be in four core PVC insulated cable not less than 0 75mm2 24 0 2mm All fuses must be ASTA approved to BS 1362 The length of the conductor between the cord ancho...

Страница 16: ...16 Concord CXS Installation Servicing 15 INTERNAL WIRING v violet pk pink y gyellow green or orange y yellow w white br brown r red LEGEND b blue bk black INSTALLATION INSTALLATION W4115A1020 T2...

Страница 17: ...the valve for that zone When all thermostats are satisfied also when the clock period ends all relays will be off so the zone valves which were open will remain open for the pump overrun period 17 ZON...

Страница 18: ...s Any leaks must be cured Replace all pressure test point screws 18 ZONES WITH SPRING RETURN MOTORISED VALVES IMPORTANT Terminal L2 may control the appropriate pump s directly provided that the total...

Страница 19: ...ton 4 4 Switch on the electrical supply to the boiler 5 Ensure that all system controls time switch system controls etc are calling for heat 6 Turn the boiler thermostat knob 1 to position 6 20 INITIA...

Страница 20: ...ows CXS 40 90 Boilers Refer to Frame 20 illustration Numbers in brackets in this 40 90 section also refer to Frame 20 The location of the manifold pressure adjuster 8 on the gas valve is shown in Fram...

Страница 21: ...st have regular maintenance and cleaning at least annually in order to ensure reliable and efficient operation Regular attention will also prolong the life of the boiler and should preferably be perfo...

Страница 22: ...ctrode shield and base fixing screws are tight 2 The electrodes are correctly positioned Refer to Frames 31 or 32 3 Reassemble in reverse order Refit the flue baffles cleanout cover NOx duct and casin...

Страница 23: ...3 or 24 1 Remove the NOx duct and burner front plate as previously described in Frame 26 2 On the CXS 40 50 60 remove the screws holding the HT heat shield from the LH leg of the combustion chamber Ra...

Страница 24: ...lows 1 pink 2 white 3 red Reconnect the earth terminal 5 Reassemble in reverse order ensuring that the thermostat connections are facing front before fitting the top bracket and that the capillary goe...

Страница 25: ...4 Pull out the sensor plug from the PCB and remove the strain relief bush Remove the sensor and lead 5 Fit the new sensor in reverse order ensuring that the lead is routed along the casing in the clip...

Страница 26: ...its contents into a commercial tip 35A CONTROL SENSOR POTENTIOMETER ASSEMBLY 1 Undo the thermostat knob retaining screw and pull off the knob 2 Remove the lower front panel 3 Undo the backnut and wash...

Страница 27: ...ractice together with any relevant requirements of the local gas supplier and local authority TOOLS REQUIRED z Spanners z Torque wrench z Pozi screwdriver z Mallet ASSEMBLY The combustion chamber shou...

Страница 28: ...ms a hydraulic test should be carried out at 1 1 2 times the design pressure given in Table 2 for a period of 30 minutes 12 On a pressurised system the test should be at twice the design pressure for...

Страница 29: ...pump with a maximum current of 3A is connected to the boiler pump terminals pump overrun will be in operation when the demand for heat is satisfied and will continue to run for 6 minutes Frost protect...

Страница 30: ...generator Replace PCB S4561B1047 YES YES 44 BOILER LIGHTS BUT GOES TO LOCKOUT NO Measure the flame current expect approximately 3 5 A Replace PCB S4561B1047 Check RH burner inlet and burner pressure...

Страница 31: ...ELL VR4605AB 1019 CXS 100 120 1 111 869 29D Gas control valve plug and lead assemblies CXS 40 120 1 111 870 29E CXS 40 120 1 154 734 29F CXS 100 120 1 112 431 29G CXS 100 120 1 139 269 29H 30 Spark ge...

Страница 32: ...154 867 A02 Ideal Installer Technical Helpline 01482 498376 SHORT LIST OF PARTS Key No Description Qty Product No 48 RH casing side panel white stove enamel CXS 40 1 111 650 CXS 50 60 1 111 651 CXS 70...

Отзывы: