16
Classic FF -
Propane Installation & Servicing
INSTALLATION
REAR FLUE OUTLET
Note.
Have ready to hand the M8 screw, washer
and rectangular plate supplied in the hardware
pack. For downward routing of pipes the M5
spacer (supplied in the Downward Piping Kit)
should now be fitted to the back of the boiler.
1. Lift the boiler onto the wall mounting plate
hooks as shown.
Do not use the burner / controls for lifting
2. Fit the M8 screw washer and rectangular
plate to retain the boiler.
Note.
Before fully tightening the M8 screw check the
boiler alignment, using a spirit level, and adjust
as necessary with the jacking screw.
19 CONNECTING THE FLUE TO THE BOILER
20 TERMINAL WALL PLATE
18 MOUNTING THE BOILER
1. Pull the flue through the wall mounting plate
and locate the 3 studs in the holes in the back
panel.
2. Secure the flue to the boiler, using the three M5
wing nuts provided.
3. Pull the flue extension tube and engage onto
fan, locate and secure with the M4 screw
attached to the fan.
Note.
The sealing ring studs will locate in the back panel
one way only. This will ensure that the terminal
grille is correctly aligned.
This plate allows neat concealment and full compression of
the rubber seal. Its use is not essential if the flue hole and
flue ducts have been accurately cut and the outside wall
face is flat.
1. Position the terminal wall plate over the terminal.
2. Mark and drill 4 fixing holes with an 7mm (
9/32
") masonry
drill.
3. Insert the 4 plastic plugs provided.
4. Secure the plate with 4 of the No.10 x 2" screws
provided.
Note.
If the terminal is less than 2m (6' 6") above ground
level, an approved terminal guard should be fitted. Refer to
the Contents List on Page 3.