On UCG105/135/165 air cooled versions the refrigerant head pressure is kept between two pre‐set 
values 

(10

8,5 bar ‐ 140

120 psig) 

with the unit a 21

C (70

F) ambient temperature. The declining of 

the pressure is relied to the reduction of the evaporating pressure, caused by the progressive growth of 
the ice thickness into the inverted cup molds and to the flow of air drown through the air cooled 
condenser by the fan motor. The above values are in relation as well to the ambient temperature of the 
ice maker site and they are subject to rise with the increase of this temperature. 

On UCG45/65/85/105/135 water cooled versions the refrigerant head pressure ranges between 

8.5 and 

10 bars (120

140 psig) 

being controlled by an automatic hi pressure control that energizes a water 

solenoid valve located on the water line to the condenser, which rates the cooling water to the 
condenser. On UCG165 water cooled versions the head pressure is constant at 

9.5 bar (135 psig) 

controlled by a water regulating valve. 

At starting of freezing cycle the refrigerant suction or lo‐pressure lowers rapidly to 

1.0 bar ‐ 14 psig 

then 

it declines gradually ‐ in relation with the growing of the ice thickness ‐ to reach, at the end of the cycle, 
approx. 

0

0.1 bar ‐ 0

1.5 psig 

on the models UCG45/65/85 and 0.85 and 0.2 

0.3 bar (3

4 psig) on 

models UCG105/135/165 with the cubes fully formed in the cup molds. The total length of the freezing 
cycle ranges from 23 to 25 minutes. 

DEFROST OR HARVEST CYCLE 

On UCG45/65/85105 the temperature of the evaporator thermostat, in contact with the evaporator 
serpentine, drops to a pre‐set value it changes its electrical contacts energizing the herebelow shown 
components. On UCG135/165  when the timer  changes its electrical contacts energizing the same 
components). 

COMPRESSOR 

WATER INLET SOLENOID  

VALVE HOT GAS SOLENOID VALVE 

The incoming water, passing through the water inlet valve and the flow control, runs over the 
evaporator platen and then flows by gravity through the dribbler holes down into the sump/ reservoir. 

The water filling the sump/reservoir forces part of the surplus water from the previous freezing cycle 
to go out to the 

drain

 through the overflow pipe. This overflow limits the level of the sump water 

which will be used to produce the next batch of ice cubes 

Meanwhile the refrigerant, as hot gas discharged from the compressor, flows through the hot gas valve 
directly into the evaporator serpentine by‐ passing the condenser. 

The hot gas circulating into the serpentine of the evaporator warms up the copper molds causing the 
harvest of the ice cubes. The ice cubes, released from the cups, drop by gravity onto a slanted cube 

deflector

, then through a curtained opening they fall into the storage bin. 

Содержание Gourmet UCG Series

Страница 1: ...45 UCG 65 UCG 85 UCG 105 UCG 135 UCG 165 Installation and Service Manual Ice O Matic 11100 E 45th Ave Denver Colorado 80239 1 866 PURE ICE Part Number 9081522 02 Revision 03 21 UCG GOURMET SERIES UND...

Страница 2: ...UCG GOURMET SERIES UNDERCOUNTER pg 2...

Страница 3: ...damage Notify the carrier of any concealed damage 5 Check that refrigerant lines do not rub against or touch other lines or surfaces and the fan blade moves freely 6 Check that the compressor fits sn...

Страница 4: ...Low voltage can cause faulty functioning and may be responsible for serious damage to the overload switch and motor windings Check voltage on the line and the ice maker s data plate before connecting...

Страница 5: ...proper flow of the drained water as in case of poor drainage the water ranning out from the condenser may inopportunely flow through the unit drain tubing into the ice storage bin F FINAL CHECK LIST...

Страница 6: ...the electrical circuit to the water inlet valve and to the hot gas valve C Switch ON the power line disconnect switch Unit will start up in water filling phase mode During this phase the components e...

Страница 7: ...hermostat or cube size control changes its contacts the freezing cycle ends and starts the defrost or harvest cycle E On models UCG 135 165 freezing cycle is completed through an electronic timer ener...

Страница 8: ...45 65 85 105 the length of the freezing cycle can be modified by turning the knob of the cube size control or evaporator thermostat located in frontofthe machineuntilthedesiredsizeisachieved if the t...

Страница 9: ...defrost or harvest cycle hold a handful of ice cubes against the bulb of the storage bin thermostat the icemaker switch OFF in about one two minutes Take out the ice from the storage bin thermostat Th...

Страница 10: ...UCG GOURMET SERIES UNDERCOUNTER pg 10...

Страница 11: ...compressor and through the suction line In both the accumulator and the suction line it exchanges heat with the refrigerant flowing into the capillary tube warmer before it is sucked in the compressor...

Страница 12: ...sig on the models UCG45 65 85 and 0 85 and 0 2 0 3 bar 3 4 psig on models UCG105 135 165 with the cubes fully formed in the cup molds The total length of the freezing cycle ranges from 23 to 25 minute...

Страница 13: ...and the second water cooled condenser by a specific hi pressure control HOT GAS SOLENOID VALVE The hot gas solenoid valve consists basically in two parts the valve body and the valve coil During the...

Страница 14: ...arallel to the water pump and it operates continuously only during the freezing cycle keeping the proper head press circulating air through the condenser fins On UCG135 165 the operation of fan motor...

Страница 15: ...the entire defrost harvest cycle with a factory pre set times The first key 1 replaces the Compressor Switch used on the previous electro mechanical version factory setting is ON position to energize...

Страница 16: ...er cooled version only This valve controls the head pressure in the refrigerant system by regulating the flow of water going to the condenser As pressure increases the water regulating val ve opens to...

Страница 17: ...ure Move the unit in a more suitable place Cubes too small Freezing cycle too short Review setting of DIP SWITCH keys Capillary tube partially restricted Blow charge add new gas drier after evacuating...

Страница 18: ...cuu pump Hot gas solenoid valve leaking Replace valve Undercharge of refrigerant Charge to data plate indication Discharge head pressure too high See incorrect discharge pressure Poor harvest Restrict...

Страница 19: ...not perform any adjustment until the ice making system has progressed through several complete freeze and harvest cycles in order to observe the size and quality of ice cubes and whether or not the cu...

Страница 20: ...UCG 45 65 85 105 WIRING DIAGRAM AIR WATER COOLED 230 50 60 1 pg 20 UCG GOURMET SERIES UNDERCOUNTER...

Страница 21: ...UCG 135 165 WIRING DIAGRAM ELECTRONIC TIMER VERSION 230 50 60 1 pg 21 UCG GOURMET SERIES UNDERCOUNTER...

Страница 22: ...Page 22...

Страница 23: ...and to get current warranty information Refer to it for applicable coverage In general warranty covers defects in material or workmanship It does not cover maintenance corrections to installations or...

Отзывы: