• Conveyor Set-Up
1. Determine direction of product flow. The drive is located at the discharge end of
the Model SBC. See Figure 4A.
2. Position conveyor in sequence per match-mark numbers at each end.
3. Attach supports as show in Figure 4B. Adjust elevation to required height.
NOTE: If celing hangers are used, see Ceiling Hangers section.
4. Install electrical controls and wire motor.
Ceiling Hanger Installation
If conveyors are to be used in an overhead application, ceiling hangers may have
been supplied in place of floor supports. Figure 4C shows how a ceiling hanger
mounts to a conveyor section. Ceiling hangers should be mounted at section joints.
Ceiling Hanger Rod needs to be a minimum of 3" from the inside channel. For
safety information concerning conveyors mounted overhead, refer to “Installation
Safety Precautions” on Page 3.
INSTALLATION
FLOW
(FLUJO)
DRIVE OUTSIDE
(UNIDAD MOTRIZ AL
EXTERIOR)
45° CURVES
(CURVAS DE 45°)
RIGHT HAND
(DE MANO
DERECHA)
LEFT HAND
(DE MANO
IZQUIERDA)
DRIVE OUTSIDE
(UNIDAD MOTRIZ AL
EXTERIOR)
DRIVE OUTSIDE
(UNIDAD MOTRIZ AL
EXTERIOR)
FLOW
(FLUJO)
60° CURVES
(CURVAS DE 60°)
FLOW
(FLUJO)
90° CURVES
(CURVAS DE 90°)
ADJUST TO
DESIRED
ELEVATION
(ADJUSTE A LA
ELEVACION
DESEADA)
MSN END ONLY
(SOLO EXTREMO MSN)
MSC
Support Pipe
(Tubo De Soporte)
Ceiling Hanger Rod
(Varilla Colgante Al
Techo)
Space Channel
(Canal Espaciador)
Jam Nut
(Contra Tuerca)
Pipe Retainer
(Abrazadera)
Jam Nut
(Contra Tuerca)
Lock Bolt
(Tornillo Candado)
Ceiling Hanger Rod
(Varilla Colgante Al
Techo)
Spacer
(Espaciador)
Jam Nut
(Contra Tuerca)
Support Pipe
(Tubo De Soporte)
Jam Nut
(Contra Tuerca)
Lock Bolt
(Tornillo Candado)
Pipe Retainer
(Abrazadera)
FIGURE 4A
FIGURE 4B
FIGURE 4C