HYDAC FILTER SYSTEMS GMBH
Putting the FCU into operation | 6
BeWa FCU1310 3371346g en-us lq
41 / 148
6 Putting the FCU into operation
Before operation, the FCU must first be hydraulically and elec-
trically connected, as described below.
6.1 Connecting / disconnecting the power supply
The FCU has a 3-pole socket for connection with a 24 V DC
power supply.
Fig. 15:
Connecting the
power supply
1.
Insert the 3-pole socket plug, e.g. of the power pack,
into the socket until the ratchet can be heard to click in
(
). Connect the other end with the voltage
source.
2.
Once the FCU is supplied with voltage, the display will
show "HYDAC FCU 1###" in ticker format. Afterwards,
the firmware version will be shown for 2 seconds.
The internal sensors will be checked after that.
The display shows
and the
firmware of the sensors.
The self-test is followed in the display by a countdown
.
3.
The FCU is now ready for the measurement.
As long as the pump is not running and no fluid
is being pumped, the status LED will flash red,
and the display will show
. This
means that there is no oil flow present.
6.1.1 Disconnecting the power supply
To remove the power supply, press the catch (1) on the con-
nector and then pull (2) the connector out.