MP24.9743
17JUN09
SECTION III
625/625S SERIES LEVELING SYSTEMS
SYSTEM START-UP AND ADJUSTMENTS
7.) FINAL CHECK LIST
1.) With all jacks fully retracted, check the oil level. The oil
level should be within 1 inch of the top of the reservoir.
2.) Check all hose connections for leaks and check hose
routings for heat or rubbing issues. Make sure all hoses
are fastened or supported properly.
3.) Check all wiring connections for tightness and make
sure all exposed connections are protected against
moisture and corrosion. Check harness routings for heat
or rubbing issues Make sure harnesses and wires are
fastened or supported properly.
4.) Check all mounting bolts and brackets for the jacks,
power unit and/or control box are tight.
5.) Check that all indicator lights including the master
warning light and buzzer (if so equipped) are functioning
properly.
6.) Run the system with the owner to explain the correct
operation and function of the leveling system in both the
manual and automatic mode.
7.) Make sure the owner receives the owner’s manual.
Review the manual, especially cautions, with the owner.
LOCKING NUT
RUBBER BOOT
Figure 21
FOR 610 SYSTEMS
BODY
ADJUST
PRESSURE
JACK PRESSURE SWITCH
SECTION IV: INSTRUCTION SHEETS - PLUMBING DIAGRAMS - WIRING DIAGRAMS
THE FOLLOWING PAGES ARE PLUMBING DIAGRAMS FOR THE HYDRAULIC LINES
AND THE HWH AIR DUMP SYSTEM, ELECTRICAL CONNECTION DIAGRAMS
AND INSTRUCTION SHEETS FOR THE LEVEL SENSING UNIT PROGRAMMING AND ADJUSTMENT.