Figure 3-64 Installing a smart ETH gateway
Step 2 Connect one end of the ground cable available in the smart ETH gateway package
to the ground point at the lower part of the cable trough using one M4 screw, and
connect the other end to the ground point on the side of the smart ETH gateway,
as shown in
.
NO TE
The M4 screw used for connecting the ground cable to the cable trough is available in the
cable trough package.
Step 3 Install the smart ETH gateway to the guide rail, as shown in
.
1. Align the upper slot of the guide rail for the smart ETH gateway with the
upper part of the guide rail, and pre-mount it onto the guide rail.
2. Press the lower part of the smart ETH gateway to clamp the smart ETH
gateway onto the guide rail.
3. Shake the smart ETH gateway in different directions to ensure that it is
reliably installed.
----End
3.10.2 Installing an Electronic Clasp Lock
Context
NO TICE
● The electronic clasp lock is not required in the 1350 mm deep scenario.
● In the 1600 mm deep scenario, an electronic clasp lock needs to be installed on
the front and rear doors of each smart cooling product and IT equipment. The
position of the electronic clasp lock depends on the positioning plate.
● An electronic clasp lock needs to be installed on the front door of the PDF only
in the cold aisle containment scenario, but cable connection is not required.
FusionModule2000-S Smart Modular Data Center