PowerCube 5000 (SUN2000-150KTL-S0)
Installation Guide
9 Power-on and Commissioning
Issue 03 (2020-04-10)
Copyright © Huawei Technologies Co., Ltd.
85
Figure 9-10
BIM
(1) RUN/ALM indicator
(2) Networking switch
Step 3
Perform networking operations on the next BIM only after networking for the previous BIM
is successful. Repeat
to add other BIMs to the CIM network.
BIMs need to be networked in ascending order of battery number.
Step 4
Hold down the networking switch on the CIM for 2s. When the RF_Z indicator on the CIM
turns from blinking green at super short intervals to blinking green at long intervals, the
networking is complete.
After the networking is complete, if the CIM ALM indicator is steady on, the number of devices online
is less than the number of BIM nodes. Check that the number of BIMs is correctly set and that the BIM
is successfully networked.
Step 5
(Optional) If multiple CIMs are cascaded, repeat
to
other CIMs and BIMs.
----End
9.7 Shutdown and Power-Off
9.7.1 Shutting Down and Powering Off a Single System
Prerequisites
Ensure that the output load is transferred or there is no major load so that system power-off is
allowed. Once the integrated equipment is shut down, there is no power output from the
output end.