background image

To avoid damaging the equipment, exercise 
caution when removing the packing materials.  

Removing the Packing Materials 

3.2 

1. Move the PDC to the specified installation 

position using a pallet truck.  

2. Cut off and remove the binding straps, as 

shown in the figure.  

3. Remove the packing materials and foam.  
4. Remove the plastic bag, take out the fitting box, 

and put it aside.  

PDC Installation 

Moving the PDC 

The PDC is heavy. Take protective measures during movement to prevent personal injury.  

Move the cabinet with caution to avoid bumping or toppling, which may damage the equipment.  

NOTICE

NOTICE

1. Move the PDC to the 

specified installation 
position.  

2. Remove the bolts 

from the pallet under 
the PDC, as shown 
by (1) in the figure.  

3. It is recommended 

that six people work 
together to move the 
PDC away from the 
pallet, as shown by (2) 
and (3) in the figure.  

4. Adjust the PDC 

leveling feet using a 
wrench to ensure that 
all castors touch the 
ground.  

1. (Optional) Check whether the tiltwatch indicator on the carton has turned red. If yes, record the 

information and contact the equipment carrier and the local Huawei office immediately.  

2. Visually inspect the equipment appearance to check whether the equipment is paint-peeling, 

deformed, scratched, or soaked. If yes, record the information and contact the equipment carrier 
and the local Huawei office immediately.  

3. Check the equipment and fittings against the packing list, and ensure that the equipment and 

fittings are correct and complete. If any fitting is missing or does not comply with the model in 
the packing list, record the information and contact the local Huawei office immediately.  

Содержание PDU8000 Series

Страница 1: ...HUAWEI TECHNOLOGIES CO LTD PDU8000 UPS PDC V1 0 Quick Installation Guide Issue 03 Date 2017 01 15 ...

Страница 2: ...n this document can be performed selectively based on the actual configurations Preparing Technical Documents 2 1 Technical Document Purpose Obtaining Method Remarks Installation Port Diagram Shows the installation port of the PDC Delivered with the product Schematic Diagram Shows the logic control relationship of circuit breakers in the PDC and the connection positions of input power cables outpu...

Страница 3: ...ion personnel and technical support personnel should prepare tools based on site requirements Prepare firestop putty for sealing cable holes after cable connection Huawei does not provide the firestop putty The customer needs to purchase it NOTE 2 Phase sequence meter Cable tie 3 Acceptance Guide After the equipment is delivered to the installation site representatives from the customer and Huawei...

Страница 4: ...n the figure 3 It is recommended that six people work together to move the PDC away from the pallet as shown by 2 and 3 in the figure 4 Adjust the PDC leveling feet using a wrench to ensure that all castors touch the ground 1 Optional Check whether the tiltwatch indicator on the carton has turned red If yes record the information and contact the equipment carrier and the local Huawei office immedi...

Страница 5: ...g washer and flat washer 1 M12 bolt 2 Spring washer 3 Flat washer 4 Expansion sleeve 5 Concrete floor Optional Installing the PDC on a Concrete Floor 4 9 Level the PDC using a level and an adjustable wrench 1 Wrench a leveling foot clockwise to elevate the cabinet or wrench a leveling foot counterclockwise to lower the cabinet The feet can be adjusted within a range of 0 8 mm 2 To prevent cabinet ...

Страница 6: ...cabinets need to be combined just partially tighten the bolts NOTE When cabinets need to be combined just partially tighten the bolts Optional Combining Cabinets 1 A connecting plate is initially secured by one screw Remove the screw from the column of the adjacent cabinet and use the screw to secure the connecting plate 2 Ensure that both the vertical deviation and the distances between cabinets ...

Страница 7: ...Terminals 1 Cable 2 Cord end terminal 3 Crimping tool Preparing Cord End Terminals 5 Cable Installation 6 Connection Method Connecting Cables 5 2 1 Ensure that all circuit breakers including upstream output circuit breakers are switched to OFF before connecting cables 2 DT and OT terminals must be coated with a heat shrink tubing 3 After cables are connected seal the cable inlet and outlet holes u...

Страница 8: ... cable into the PDC b Connect the input N cable and PE cable to the corresponding N bar and PE bar c Connect the phase cables to the corresponding input terminals of phases L1 L2 and L3 7 Connect the output cables based on the Schematic Diagram delivered with the product as shown by 4 in the figure a Connect one PE cable and one N cable from the PE bar and N bar inside the PDC to each load b Conne...

Страница 9: ...d reinstall them in the PDC 8 Optional Connecting Cables for the UPS Input and Output PDC 1 Connect the PE cable Secure one end of the ground cable to the ground bar inside the PDC and secure the other end to the ground grid or busbar of the equipment room 3 Connect the UPS input power cables NOTE 2 Connect the mains input power cables ...

Страница 10: ...er cables 5 Connect the mains output power cables for air conditioners and other loads a Optional MCCB output scenario b Optional Single phase output with a 1P output switch c Optional Single phase output with a 2P output switch 9 ...

Страница 11: ...MCB output scenario 6 Connect the UPS load output power cables a Optional MCCB output scenario b Optional Single phase output scenario with a 1P output switch c Optional Single phase output scenario with a 2P output switch 10 ...

Страница 12: ...e Secure one end of the ground cable to the ground bar inside the PDC and secure the other end to the ground grid or busbar of the equipment room 7 Connect signal cables d Optional Three phase MCB output scenario NOTE 11 2 Connect the mains input power cables 3 Connect the UPS input power cables ...

Страница 13: ...2 Optional Connecting Cables for the UPS Output PDC 1 Connect the PE cable as shown in the figure Secure one end of the ground cable to the ground bar inside the PDC and secure the other end to the ground grid or busbar of the equipment room 2 Connect the input power cables NOTE ...

Страница 14: ...on the cabinet exterior is intact Pass Fail 3 The cabinet door and lock work properly Pass Fail 4 All safety marks and warnings are correct clear and complete Pass Fail 5 There is no adhesive tape cable tie paper scrap or packing material around the cabinet Pass Fail No Check Item Check Result 1 All cables are connected correctly Pass Fail 2 Ground cables are securely connected Pass Fail 3 Power c...

Страница 15: ...ect using a phase sequence meter In the ATS input scenario check the phase sequences of both power inputs 5 Turn on the upstream switch of the SPD 6 Turn on the input circuit breaker of the PDC and check whether the voltage and frequency on the electric meter are normal 7 The PDC power on check is completed 1 Check cable connections and the mechanical performance Check that cables are connected co...

Страница 16: ...tch on other circuit breakers as shown in the figure Check that the insulation resistances of the power distribution devices and feed circuit are no less than 0 5 megohm After checking turn off all the circuit breakers 1 Check cable connections and the mechanical performance Check that cables are connected correctly outside the cabinet Check that all bolts are secured for inlet and outlet cables a...

Страница 17: ...m Terminal Bolt Specifications Recommended Torque N m Power input L N 160 50 DT M10 27 200 70 DT M12 47 250 95 DT M12 47 400 185 DT M12 47 630 2x185 DT M12 47 Power input PE 160 25 DT M10 27 200 35 DT M10 27 250 50 DT M10 27 400 95 DT M12 47 630 2x95 DT M12 47 AC output L 10 2 5 Cord end terminal insertion depth 8 12 mm 1 6 10 I 40 6 Cord end terminal insertion depth 8 12 mm 1 6 40 I 63 10 Cord en...

Страница 18: ...port huawei com Support Support E WeChat Google Play Scan here for technical support enterprise Scan here for technical support carrier Google Play Huawei App Store Huawei App Store Huawei Technologies Co Ltd Huawei Industrial Base Bantian Longgang Shenzhen 518129 People s Republic of China www huawei com Apple Store Apple Store ...