IDS2000 Dual-Row Aisle Containment
Installation Guide (Split-type Skylight, Old-Version
Sliding Door)
2 Installing Cabinets
Issue 02 (2015-06-30)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
29
Procedure
Step 1
Install cabinet sealing plates, and secure them using M6x16 tapping screws, as shown in
The flanges of cabinet sealing kits must face the outside of the cabinet.
Do not install sealing plates to the four cabinets that are located at both ends of each row
until you install the end doors. Front cabinets can be integrated cabling cabinets, server
cabinets, or PDU8000s.
Figure 2-32
Installing cabinet sealing plates
----End
2.5.2 Removing Rack Power Distribution Unit
This section describes how to remove industrial connectors and cables from the rack power
distribution unit (PDU2000).
Procedure
Step 1
Remove the rodent-proof mesh above the PDU2000 at the top of the cabinet, and take out two
PDU2000 industrial connectors, as shown in
If the PDU2000 does not have an industrial connector, take out its cables and place them on the top of
the cabinet.