IDS2000 Dual-Row Aisle Containment
Installation Guide (Split-type Skylight, Old-Version
Sliding Door)
2 Installing Cabinets
Issue 02 (2015-06-30)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
24
Figure 2-23
600 mm wide top frame of air conditioners
Procedure
When the air conditioner pipes are routed underfloor, perform the following steps:
Pay attention to the installation direction of the top frame of the air conditioner. Face the end
with holes to the end of the air conditioner pipe outlets.
a.
Remove the top panel of the air conditioner, as shown in
Figure 2-24
Removing the top panel of the air conditioner
b.
Secure the top frame to the top of the air conditioner, as shown in