FusionModule5000 Smart Modular Data Center
Installation Guide (Single-Row Aisle Containment with
2000 mm High Cabinets, ECC800)
6 Installing the Contained Aisles
Issue 01 (2019-03-05)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
88
Figure 6-13
Assembling the front and rear sealing plates
Step 2
Secure the front and rear sealing plates to the cabinet using four M5x10 tapping screws, as
shown by (1) in
Figure 6-14
Securing a sealing plate
Step 3
Place the side sealing plate with the side with dents upward, and snap the side sealing plate
into the front and rear sealing plates, as shown by (2) in
----End