FusionModule5000 Smart Modular Data Center
Installation Guide (Single-Row Aisle Containment with
2000 mm High Cabinets, ECC800)
4 Hardware Installation Preparations
Issue 01 (2019-03-05)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
23
Figure 4-2
Measuring the floor height
2.
Adjust the base height to H based on the measured value, as shown by (1) in
3.
Partially tighten the height-locking bolts on two sides, as shown by (2) in
Figure 4-3
Partially tightening the height-locking bolts
Step 2
Assemble the base, as shown in