2-6
Installing the Switch
Installation Procedures
2. Verify the Switch Passes Self Test
Before mounting the switch in its network location, you should first verify it
is working properly by plugging it into a power source and verifying it passes
its self test.
1.
For the Switch 2520G-24-PoE, connect the power cord supplied with the
switch to the power connector on the back of the switch, and then into a
properly grounded electrical outlet.
For the Switch 2520G-8-PoE, connect the AC/DC adapter’s power cord to
the power connector on the back of the switch, and then plug the AC/DC
power adapter into a nearby properly grounded electrical outlet.
Figure 2-1. Connecting the power cord
N o t e
The Switch 2520G-24-PoE does not have a power switch. It is powered on
when the power cord is connected to the switch and to a power source. For
safety, the power outlet should be located near the switch installation.
Connect power cord to
the power connector
Switch 2520G-8-PoE
Switch 2520G-24-PoE
Connect AC/DC power adapter to the
switch and an AC power outlet
Содержание ProCurve 2520-PoE
Страница 1: ...HP ProCurve 2520G PoE Switches Installation and Getting Started Guide Power over Ethernet ...
Страница 2: ......
Страница 3: ...HP ProCurve 2520G PoE Switches Installation and Getting Started Guide ...
Страница 20: ......
Страница 46: ......
Страница 52: ......
Страница 66: ......
Страница 85: ...B 7 Safety and EMC Regulatory Statements Safety Information China Safety Information China ...
Страница 87: ...B 9 Safety and EMC Regulatory Statements EMC Regulatory Statements Korea Taiwan ...
Страница 88: ...B 10 Safety and EMC Regulatory Statements EMC Regulatory Statements European Community ...
Страница 89: ...B 11 Safety and EMC Regulatory Statements EMC Regulatory Statements ...
Страница 90: ......
Страница 100: ......