8.
Tie wrap the processor cable to the right tie point on the processor assembly.
CAUTION:
When the CPU is installed, dress all slack in the power cable to the connector
end of the cable. Failure to do so could result in pinched or damaged CPU power cables.
NOTE:
If you are adding an additional processor to your server blade, the DIMMs in the server
blade must be reconfigured to support both CPUs. See
“DIMM pair load order” (page 27)
for
more information.
Installing DIMMs
DIMM installation guidelines
Observe the following guidelines when installing additional memory:
•
In a BL860c i2, memory is loaded in pairs.
•
In a BL870 i2 or BL890 i2, memory is loaded in quads that alternate between blades.
•
Only 2 DIMM sizes can be mixed in a BL870 i2 or BL890 i2.
— In a BL870c i2, the two DIMM sizes must alternate between blades. Load all of one
DIMM size, then repeat with the second DIMM size.
— In a BL890c i2, blade configuration, blades 1 and 2 must have one DIMM size and blades
3 and 4 must have the other DIMM size.
26
Installing the server blade into the enclosure
Содержание Integrity BL890c - i2 Server
Страница 5: ...List of Tables 1 1 DIMM pair load order 27 1 2 DIMM quad load order 28 1 3 Power States 41 5 ...
Страница 6: ...6 ...
Страница 46: ...46 ...
Страница 50: ...50 ...