Make the following cable connections to complete the installation of the second
drawer:
•
Connections from the power subrack to the AC input box (if not made
already)
•
Power signals to the drawer
•
48V/48RTN; Vaux/VauxRTN connections to the drawer
•
Fan power/signals to the drawer
•
CSB connections
Refer to Appendix A for a wiring diagram illustrating the above connections.
Make sure that the CSB (console serial bus) between the J9 connector of the
master PCI box and the J6 connector of the drawer is properly connected and
terminated at both ends.
Proceed as follows:
1. Attach the power and signal cables from the power subrack to the new
drawer
. Route the cables as needed and attach the cables to the frame
with cable ties.
2. Attach the cable management bracket to the rear of the cabinet behind the
new drawer. Use two M6 screws on each side of the bracket to fasten it to
the cabinet frame where the drawer slide rails are attached.
3. Attach the CSB junction block to the side of the cabinet frame near the new
drawer
(Figure 3-4 shows details on CSB junction block attachment).
Then, attach the CSB cable from this junction block to the drawer
. Now,
connect the new CSB junction block to the existing junction block with
twisted-pair cable. Be sure to terminate any unused connections on the
junction blocks.
Make any hose cable connections from the local I/O riser ports on the drawers to
the remote risers in the PCI box.
The GS80 upgrade is complete. Turn on the system and verify the operation of
the new drawer.
Содержание AlphaServer GS80
Страница 4: ......
Страница 8: ......
Страница 29: ...System Upgrade 2 13 Figure 2 7 Cable Connections 4 FOLD 9 PK3224 10 ...
Страница 32: ......
Страница 48: ......