23
Verification Procedure
The following verification procedures assume you understand how to operate the ac source from the front
panel as explained in chapter 4.
Perform the following tests for operation verification in the order indicated.
1. Turn-On Checkout
2. Voltage Measurement Accuracy
3. Current Measurement Accuracy
NOTE:
The ac source must pass turn-on selftest before you can proceed with the verification.
Test Set up
COM
R
Rs
L
Rs = Current Monitor resistor (0.01 ohms)
HP3458A
DMM
COM
01
SENSE
R = Load resistor for CC test (30 ohms)
01
HP3458A
DMM
HP 6811B/6812B/6813B
MAIN OUTPUT
POWER ANALYZER
LO HI | LO HI
I
SENSE
V
SENSE
HP33120A
FUNCTION GENERATOR
COM
COM
01
SENSE
01
HP 6811B/6812B/6813B
MAIN OUTPUT
POWER ANALYZER
LO HI | LO HI
I
SENSE
V
SENSE
HP3458A
DMM
C1
C1 = Capacitor (1.0 uF)
A.
B.
LO
HI
LO
HI
LO
HI
L
Figure B-1. Verification / Calibration Test Setup