![background image](http://html1.mh-extra.com/html/hoval/uno-3-110/uno-3-110_technical-information-and-assembly-instructions_2170760005.webp)
5
4 205 116 / 02
Installation
1. Pull up the semicircular rivet (1).
2. Change over the swivel arm (2).
3. Insert the semicircular rivet (1) on the other side.
4. Fit the burner plug and the fire protection switch
(if fitted, Austrian version) on the other side
(see point 2.3, item 9 and point 4.5.1).
The cable must not touch any hot
parts!
Levelling
Using a spirit level, align the upper edge of the
boiler water jacket (longitudinal axis of the boiler)
until it is precisely horizontal or sloping very slightly
upwards towards the rear by inserting the plinth
rails correspondingly, to allow the boiler to vent
properly.
Before fitting the burner, first fit the double
door (Pos. 8b, Figure 7) (door casing).
2. Installation
2.1 Setting up, levelling
A special foundation plate for the boiler is not an
essential, but it is recommended.
Space requirement
for mounting the thermal insulation and sheet metal
cladding:
at least 40 cm each on the left and right side of
the boiler.
If the space between the boiler and the wall is less,
all heat insulation and casing must be fitted before
the boiler can be pushed into its final position.
Do not connect lines until the heat insulation
and casing have been fitted to the boiler!
There must always be enough space between
the back of the boiler and the wall to allow
easy access to the cleaning aperture in the
flue gas collector.
There must be enough space to swing open the
boiler door, incl. the burner.
Do not overtighten boiler door screws.
Fig. 2
1
2
Boiler door pivotable to the left
It is possible to change the attachment of the boiler
door so that it opens towards the left. This can be of
advantage when installing the boiler in a corner.
Proceed as follows:
Close the boiler door and lock it in position
before changing the attachment of the door.