8. Series 8 I/O
Loading
8.5. Loading a CM
234
Series 8 I/O User's Guide
R500
Honeywell
April 2017
Usually, after performing an upload to the database, you should also update the data to
Project so that both the Monitoring and the Project databases tally.
Refer to Using Upload command in the
Control Building User’s Guide
for information
about uploading.
Update to Project
Update to Project Series 8 I/O blocks does not differ from update to Project of other
Experion blocks. All loadable parameter values are copied from the Monitoring tab to the
Project tab.
Reviewing the Update function
A major part of the hierarchical building, CM/SCM containment allows the user to
contain CM(s) or /SCM(s) into another CM.
If a projected CM/SCM is updated to project:
All its projected parameters are checked to ensure that the projection chain
downwards to the origin is valid, which includes the validation of both origin
parameters and projected connections.
Read only connections are not updated to project directly. Only projected
connections are updated.
In addition, the Update operation fails for any reason, the projected parameter
remains, but the origins of the projected parameter is emptied.
Using IOM Checkpoint
Checkpoint of Series 8 I/O blocks does not differ from checkpoint of other blocks being
checkpointed.
Refer to Checkpoint Replaces Snapshot in the
Control Building User’s Guide
to review
checkpoint information.
8.5 Loading a CM
Loading the CM the first time
The CM load operation loads the CM block and standard blocks to the assigned CEE
function block and load the contained IOC block parameters to the IOM device.
Refer to Loading a CM in the
Control Building User’s Guide
for information about
loading a Control Module and its associated Control Execution Environment (CEE). The
load procedure is similar for all control environment related components.
Upload error conditions
The following conditions return load errors: