18
FSC Safety Manager Installation Guide
10/01
1.4
Unpacking and Placement,
Continued
Roller method
As illustrated in Figure 1-12, using the roller method the FSC Safety
Manager is moved to its final destination by placing pipe rollers under a
transport skid made of angle iron. Table 1-6 lists special considerations
regarding the use of the roller method to move the equipment.
Table 1-6 – Roller method considerations
Number
Consideration
1
Use one of the previous methods to move the cabinet to a location
where rollers are to be used.
2
Install the angle iron transport skid as in the mobile lifter method.
3
Place 12 mm (1/2 inch) pipes under the transport skid as in Figure
1-12.
ATTENTION
The load must be on the angle irons, not the
cabinet.
4
Roll the cabinet to its final location.
ATTENTION
At least three pipes must be under the transport
skid at all times.
5
When the cabinet is near the final location, tilt it and pull out the
pipes, the middle one last.
6
Dismantle the transport skid and position the cabinet manually to
the exact final location.
Figure 1-12 – Lifting equipment by mobile lifter of crane — part 2
2.5 cm (1 in) pipes (minimum)
Angle iron
supports
Continued on next page
Содержание FSC-SM
Страница 2: ... ...
Страница 6: ...iv FSC Safety Manager Installation Guide 10 01 ...
Страница 12: ...x FSC Safety Manager Installation Guide 10 01 ...
Страница 32: ...20 FSC Safety Manager Installation Guide 10 01 Left blank intentionally ...
Страница 54: ...42 FSC Safety Manager Installation Guide 10 01 Left blank intentionally ...
Страница 70: ...58 FSC Safety Manager Installation Guide 10 01 Left blank intentionally ...
Страница 74: ... ...
Страница 75: ... ...