MLSUC500 / 1250 Installation Guide 32340084-001 Rev A, 24-Aug-2018. MU1B-0638GE51 R0718A 3

Installation Guide 

MLSUC500 / 1250

5

Connect Ethernet

6

Connect MLS Spine

3 INSTALLATION 

(continued)

The entry for wiring into the main enclosure can be made by 

drilling a conduit of around 20mm at the bottom or either side 

of the enclosure.

Default Settings

IP Address

Subnet Mask

PRI

 (LAN 1)

192.168.1.140

255.255.255.0

RJ45

Standard Ethernet cable 

(Cat 5e twisted pair) 

RJ45

Hub / Switch

Router

maximum 100 m (109 yds)

Caution: 

MLSUC500 / 1250 is not compatible with PoE 

(Power over Ethernet) networks. Connecting to a PoE 

network may cause the unit to stop functioning. In that 

event, disconnect it from the network segment and power-

cycle the MLSUC500 / 1250.

≤ 32 devices

RS-485

The MLSUC500 / 1250  assumes the role of Bus Master on 

the MLS Spine. This means that all the RB2000s should 

be given consecutive, unique non-zero addresses, refer to 

RB2000 documents.

The last unit at each end of the MLS spine should be 

configured  to  terminate  the  two  RS485  signal  pairs,  A-B 

and Y-Z. In the case of an RB2000 being the last device this 

is simply a matter of sliding the switch behind the address 

setting switches to the ON position.

The entry for wiring into the main enclosure can be made by 

drilling a conduit of around 20mm at the bottom or either side 

of the enclosure.

Note: The spine connections from the MLSJ8 are prewired to 

the terminal blocks.

B

A

Screen

Z

Y

B

A

Screen

Z Y

to further

remote 

RB2000’s

MLSUC500 / 1250

 

RB2000

Содержание Ex-Or MLSUC500

Страница 1: ...500 1250 Installation Instructions Mounting 32340084 001 and enclosure mounting instructions 4 Field Maintenance 4 5 Disposal 4 H O 2 85 C 5 40 C 95 RH 185 mm 7 25 300 mm 11 75 Allow Cover clearance Unit with door open It is recommended that the installation should comply with the local electrical safety installation practices e g HSE Memorandum of Guidance on Electricity at Work Regulations 1989 ...

Страница 2: ...ocation subject to electrical noise H O 2 60 C 5 20 C 95 RH The entry for the power wiring can be made by drilling a conduit of around 20mm at the bottom or either side of the enclosure The power wiring must be terminated at the MLS power terminals and circuit breaker and terminal blocks The MCB and the terminal blocks are prewired to the MLSJ8 PSU in the factory Note the MLS circuit breaker and M...

Страница 3: ...In that event disconnect it from the network segment and power cycle the MLSUC500 1250 32 devices RS 485 The MLSUC500 1250 assumes the role of Bus Master on the MLS Spine This means that all the RB2000s should be given consecutive unique non zero addresses refer to RB2000 documents The last unit at each end of the MLS spine should be configured to terminate the two RS485 signal pairs A B and Y Z I...

Страница 4: ...ycling centre Do not dispose of with normal household waste Do not burn 5 FIELD MAINTENANCE MLSUC500 1250 requires no routine maintenance WARNING Contains no serviceable parts Do not attempt to open the unit Failure to comply may cause damage to the unit 3 INSTALLATION continued MLSUC500 1250 Configuration Manual W6003 The following information will be useful RB2000 locations Zones and their respe...

Отзывы: