Commissioning:
1. Check all electrical connections (Figs. 2
and 3).
2. Make sure that the controller software is
EET.
3. Check / Set Bit Switches (Fig. 1).
4. Switch the controller ON.
5. Connect Set-up Unit to DIN Box Display
or controller (Fig. 2).
6. Check / Set operating parameters - see
list
7. Save values - if changed
8. Log the controller on to the network then
verify settings on Genus InTouch panel,
Set-up Unit or DIN Box Display.
9. Faults ?..........See ‘Fault Finding’.
Fault Finding:
Set-up Unit does not reach the first
screen.
•
If the red LED beside the display
connector is ON, then the controller is
faulty.
You cannot log the controller on to
the network.
•
There may be a controller with the same
name, already logged on the network.
•
There may be a maximum 32 controllers
already on the network segment.
•
Check on the InTouch panel, P.C. or
Supervisor.
Parameter
DIN
Range/Units
Default
HT(LT)
Dsgn
Act.
Cut in Temperature
0
-49 to 30 / °C
0 (-20)
Air On / Off Weight
1
0 to 100 / %
50
OT Alarm
3
-49 to 60 / °C
5 (-16)
UT Alarm
2
-49 to 60 / °C
-2 (-25)
Alarm Delay
4
00:00 to 99:00/Min:Sec
20:00
Defrost Start
5
00:00 to 23:59/Hrs:Mins
01:00
Number of Defrosts per Day
6
0 to 8
6
No Defrost Time
7
0 to 25 / Hrs.
7
Gas Defrost Detect
8
0 to 30 / °C
18
Defrost Terminate Temperature
9
-49 to 30 / °C
10 (14)
Defrost Minimum Time
10
00:00 to 99:00/Min:Sec
05:00
Defrost Maximum Time
11
00:00 to 99:00/Min:Sec
24:00
(25:00)
Drain Down Time
12
00:00 to 20:00/Min:Sec
01:30
Defrost Recovery Time
13
00:00 to 99:00/Min:Sec
30:00
Defrost Type: 0=Elect.; 1= 2Gas
; 2= 3Gas
14
0 to 2
0
Defrost Mode: 0=Local ;
1=Remote
15
0 to 1
0
Defrost Hold: 0=Off ; 1=On
16
0 to 1
0
Fans in Defrost: 0=Off ; 1=On
17
0 to 1
1
Hour
18
0 to 23
Minute
19
0 to 59
Day
20
0 to 31
Month
21
0 to 12
Year
22
0 to 99
BST / GMT Select: 0=Auto ;
1=Man.Off ; 2=Man.On
23
0 to 2
0
Lights / Blind: 0=Local ;
1=Remote ; 2=Man.Off ;
3=Man.On
24
0 to 3
0
Sunday (Blinds) Up / Down
25/26
00:00 to 23:59/Hrs:Mins
08:00/20:00
Monday Up / Down
27/28
00:00 to 23:59/Hrs:Mins
08:00/20:00
Tuesday Up / Down
29/30
00:00 to 23:59/Hrs:Mins
08:00/20:00
Wednesday Up / Down
31/32
00:00 to 23:59/Hrs:Mins
08:00/20:00
Thursday Up / Down
33/34
00:00 to 23:59/Hrs:Mins
08:00/20:00
Friday Up / Down
35/36
00:00 to 23:59/Hrs:Mins
08:00/20:00
Saturday Up / Down
37/38
00:00 to 23:59/Hrs:Mins
08:00/20:00
Superheat reference
39
8.0 (6.0)
EEV Proportional Gain
40
2.00
EEV Integral Gain
41
2.00
EEV Integral Time
42
Do not change the
03:00
EEV Size
43
value of these
1.0
EPR Gain
44
parameters
0.70
EPR Integral Time
45
00:15
Temp. Proportional Gain
46
1.5
Temp. Integral Gain
47
0.7
Temp. Integral Time
48
10:00
Manual Defrost: 0=Off ; 1=On
99
0 to 1
0
EET004s 7B30FE
Display Alarm Messages:
AL
Temperature alarm
Ft
Probes 1 and 2 are faulty
Pn
probe ‘n’ faulty or not connected
(Where ‘n’ = probe number)
EE
EEPROM fault
rr
Internal program fault
En
Plant fault (‘n’ = number)
Store:.............................................
Controller
Name:
Designer:........................................
Date:..............................................
Engineer:........................................
Date:..............................................
Universal Controller -
ST Case
ZA-10067-EET
Issue a : 14/5/97
E N N N N E
E N N N E
Lights
RL5
L
ig
h
ts
/
B
li
n
d
s
/
A
la
rm
S
a
tu
ra
te
d
g
a
s
v
a
lv
e
/
D
e
fr
o
s
t
h
e
a
te
r
E
le
c
tr
o
n
ic
e
x
p
a
n
s
io
n
v
a
lv
e
S
u
c
ti
o
n
l
in
e
v
a
lv
e
Solenoids
RL1
RL3
RL2
RL4
Fans
Not used
Fans
N
o
t
u
s
e
d
L
L Line
N Neutral
E Earth
F3
F2
F4
F1
Output Connections (Fig. 3)
Top
Bottom
Output Connections (Fig. 3):
The diagram on the left shows the output
connections to the EEV and suction line valves,
SGV or defrost heater, lights, blinds and alarm.
The connection to the EPR valve is made from
the front panel, at the two-pin connector
labelled ‘EPR valve’.
A special cable is provided for the network
connection. Neighbouring controllers can be
linked together to form a network by connecting
these cables in series.