7. Connection diagram
Important note
- If several power supplys are used for increasing the emergency power capacity, the 0 V potentials of all power
supplys must be interconnected via KL103/KL104.
Accum. fault
Output
SE
Fault
Fault
+12V DC
0V
Mains
U_bat
Charger controller defective
Mains missing
Fault U_ext.
SE active
Reset key
Fault U_ext.
!U_bat<
Test
U_bat < 10.5V
0V
S100
Accum. 1
Accum. 2
Si102
Si103
ST103
Secondary voltage 24V
Secondary voltage 15V
+24V DC
0V
NTC100
When using an external NCT,
DB102 must be debridged
These Potis (PO101, PO102)
may not be adjusted
Bore holes for
soldering the
connection cable of
the external NTC
0V
internal test voltage
+12V DC
Ext. user 1
Ext. user 2
0V
0V
Mains
230V AC
Ext. user
230V AC
Potentiometer
PO 100 charge terminating voltage
Fuses:
Si100
1.6 AT External user 1 +12 V DC
Si101 1.6 AT External user 2 +12 V DC
Si102 8 AT
Accumulator charging
Si103 1 AT
Output 24 V DC
Si104 2 AT
Primary fuse
Si105 1 AT
External user 230 V AC
LED Indication:
LD1
Accumulator fault
LD2
U_BAT <10.8 V switch-off warning
LD3
U_BAT <10.5 V switch-off of power
supply
LD4
U_BAT <9.45 V accumulator defective
LD5
Charger controller defective
LD6
Mains voltage missing
LD7
Fault external user
LD8
Fault input SE actuated
DIP Switch S100
Fault messages can be switched through to
collective fault with S100.
The respective switch must be at the "ON”
position.
S100/1 Fault - external user
S100/2 Mains fault
S100/3 Accumulator defective (<9.45 V)
S100/4 Charger controller defective
For VdS compliant applications, the following
settings apply:
S100/1 = OFF
S100/2 = OFF
S100/3 = OFF
S100/4 = OFF
Wire Jumpers:
DB100: Open, when the non-fused earth
conductor registers faults
DB101: Open during continuous operation
without accumulator
(not Vds-compliant)
DB102: Open, when external NCT is
connected
Before opening the housing, wait
until the electrolytic capacitors are
discharged (approx. 3 minutes).
Please observe Chapter 2 and 3
in these instructions!
PO 100
0V
internal test voltage
+12V DC
Mounting and Connection Instructions Mains/charger unit 12 V DC / 80 Ah 7
*
*
*
Charge terminating voltage