25
OPERATION
STANDBY POWER
Connections to a Building’s Electrical System
Connections for standby power to a building’s electrical system must
be made by a qualified electrician. The connection must isolate the
generator power from utility power, and must comply with all
applicable laws and electrical codes.
In some areas, generators are required by law to be registered with
local utility companies. Check local regulations for proper registration
and use procedures.
System Ground
This generator has a system ground that connects the generator frame
components to the ground terminals in the AC output receptacles. The
system ground is not connected to the AC neutral wire.
Improper connections to a building’s
electrical system can allow current from the
generator to backfeed into the utility lines.
Such backfeed may electrocute utility
company workers or others who contact the
lines during a power outage, and the
generator may explode, burn, or cause fires
when utility power is restored.
Consult the utility company or a qualified
electrician prior to making any power
connections.
42Z368100.book 25 ページ 2014年4月4日 金曜日 午後3時44分