APCQ CAPACITOR BANKS
STATUS
Approved
SECURITY LEVEL
Public
DOCUMENT ID
9AKK107680A4136
REV.
E
LANG.
en
PAGE
40/47
© 2022 Hitachi Energy. All rights reserved.
APCQ - Maintenance check list
Issued by:
Date:
Regular maintenance procedure
OK/NOK
−
Check ambient temperature and equipment ventilation (should be within specification).
−
Isolate the APCQ capacitor bank from power supplies.
−
Open the front door panel.
−
Clear air inlet and outlet.
−
Clean all parts from dust and dirt.
−
Check fuses (shouldn’t be brown).
−
Switch on each power step manually with RVC/RVT Controller.
−
Check contactors and their good operation – replace them if necessary.
−
Check operation of RVC/RVT Controller.
−
Measure capacitors currents (in the three phases) for every power step and record the
measurements1.
QCap
I Phase A
I Phase B
I Phase C
I Nominal
OK/NOK
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
Fan replacement
OK/NOK
Fans have to be replaced every 5 years (40 000 hours)
1
current measurements should be compared to previous measurements. If current is 10% lower than first
measurement, capacitors have to be replaced.
Nominal current is normally given by:
𝐼𝐼
𝑛𝑛
=
𝑄𝑄
𝑥𝑥
𝑈𝑈
𝑛𝑛
√3
Where:
𝐼𝐼
𝑛𝑛
= current in one phase -
𝑄𝑄
𝑥𝑥
= Reactive power (kvar) on the power step -
√
3 =
square root of three -
𝑈𝑈
𝑛𝑛
= RMS value of phase to phase voltage