P-K DURATION II
™ Indirect Domestic Water Heating System
11
3.4.3
Boiler Water Manifold Piping (Duplex Only)
The Duration II Duplex unit is equipped with a Boiler Water Manifold to allow for easy installation. Below is an
image which shows the manifold. The Boiler water is piped to each heat exchanger from one connection point,
limiting the requirement for multiple connections, provided the same boiler water is required to feed both heat
exchangers. In a situation where the boiler water is coming in from the left side, removing the grooved tee fitting
and rotating the manifold is easily complete.
3.4.3.1
Boiler Water Manifold Piping Figure