Accentra 52i Pellet Insert Zero Clearance Cabinet
Part #1-00-574323
5
Caution should be taken NOT TO HAVE a stud within 5” of the center line
of the flue pipe. (Use PL Vent Pipe ONLY)
This should allow room for any PL Vent certified wall pass through.
The finished face of the fireplace facade, “MUST” be flush with the ZC
Cabinet front face when completed.
NOTE:
See following pages for rough-in
instructions for other facing materials.
NOTE:
When fiberglass insulation is
placed directly on top of the ZC Cabinet
it should not touch the vent pipe. The
outer ring knock out of the flue pipe
opening is designed to install a standard
6” sheet metal starter collar and a short
length of pipe to keep the insulation from
touching the vent pipe.