SPOGG Sport-Güter GmbH • Schulstr. 27 • D-35614 Asslar-Berghausen
•
www.hally-gally-spielplatzgeraete.de
\\CAD1\Huck-SG_Mont-Anl\Spogg-Mont\Englisch\2001150\Standard\20_01_150-01_en_14.doc
23
See drawings for details!
Explanations of abbreviations and symbols :
Version: climbing net chimney Art. No. 20.01.150
AB
The legal setting times of concrete must be observed
BWk
Constructive reinforcement steel installed (BWK see unit list)
D
Concrete C25/30 (for foundations)
Entf.
remove
F
Fall protection
O.K.
Upper edge of playing level
PS. (G.V.)
Legally prescribed safety area (Ø 8.00 m)
PS (D.E.)
Urgently recommended safety area (Ø 11.00 m)
G
Drainage 10 cm
Lno!
Tab ring open at the bottom
Sil
stick with silicone
Gehw.Pl.
R100
Radius 100 mm
WH!
Important NOTE
Vb Ø 4
Pre-drill 4 mm
109
Attion!
Plaese take care for the direction of the PA-Ring during Installation.
Foundation edges must be rounded off (min.R = 100 mm
Sizes of fundations are designed for soils class“4-5” (natural ground).
Soil class 4:soft to medium plasticity, interleave bound, with minor portion of stone (portion
<30% with bigger diameter of 63 mm grain size)
Soil class 5: ground with soil class 3 and 4 with big portion of stones
(portion > 30% with bigger diameter of 63 mm grain size)
IN CASE OF SANDY AND SOFT SOILS, THE SURFACE DIMENSIONS OF FOUNDATIONS HAVE
TO BE ENLARGED FOR ABOUT 50%!.
WH
The complete equipment Pos.2 needs to be installed first afterwords,
you can finally fix the post cover Pos. 110 + black cover Pos. 109 with
the self cutting screw Pos. 107 and 111 which are part of the delivery.