Pallet Pool - Placement
1
Install the Pallet Pool alignment blocks onto the
host machine's base.
Note:
The alignment block with the radius [1]
must be installed towards the front of the UMC
and the alignment block with the flat side [2]
must be installed towards the rear of the
machine.
Install the alignment bars [3] onto the pallet pool
base.
Use the forklift or the pallet jack to place the
pallet pool on the right side of the host machine.
Move the pallet pool assembly so the alignment
arms are 3 - 6” (76 - 152 mm) away from the
alignment blocks.
Install the leveling pads under the pallet pool and
lower the pallet pool.
2
Install the turnbuckles [3] with the provided
hardware (SHCS, washer, and bushings [1]) onto
the alignment arms [2] and the base casting [4].
Evenly tighten the turnbuckles until the alignment
arms mate with the alignment blocks.
UMC - Pallet Pool - Installation
Page 6 of 17 pages
Содержание UMC
Страница 1: ...LAST UPDATED 04 06 2020 UMC Pallet Pool Installation UMC Pallet Pool Installation Page 1 of 17 pages ...
Страница 2: ...Introduction UMC Pallet Pool Installation Page 2 of 17 pages ...
Страница 7: ...UMC Pallet Pool HPU Installation UMC Pallet Pool Installation Page 7 of 17 pages ...
Страница 10: ...UMC Pallet Pool Electrical Connections UMC Pallet Pool Installation Page 10 of 17 pages ...
Страница 13: ...UMC Pallet Pool Leveling and Alignment UMC Pallet Pool Installation Page 13 of 17 pages ...