HEAT RECLAIMER ASSEMBLY INSTRUCTIONS

Inlet Box Assembly

Mark a line 4.5625" (4  9/16") down from the top of the

DRYER FAN SUPPORT.

  This line will mark the top side

of the 

INLET BOX BACK PANELS

 for proper alignment.

The 

INLET BOX BACK PANELS

 meet on the centerline

of the fan cans.
Mount the 

INLET BOX BACK PANELS (D01-0566 & D01-

0567, Figure 1)

 using the 

5/16" SELF TAPPING SCREWS

included in the hardware package.
Mount the 

INLET BOX SUPPORT ANGLE (D01-0586,

Figure 2) 

to each of the 

INLET ENTRY PANELS (D01-

0572 LH & D01-0573 RH, Figure 1).

Mount the 

INLET ENTRY PANELS 

to the

 INLET BOX

BACK PANELS 

with the flanges pointing to the rear of

the dryer and the door close to the inside of the platform.
Mount the 

INLET BOX FRONT PANELS (D01-0657 &

D01-0858, Figure 1)

 to the 

LONG WALL ANGLE

 on the

SERVICE PLATFORM

.

Attach the 

INLET BOX CORNER PLATE (D01-0658, Fig-

ure 1) 

to the 

INLET BOX FRONT PANELS

 with the offset

pointing away from the dryer.
Mount the 

INLET BOX TOP (D01-0568 LH & D01-0569

RH, Figure 1)  

to the rest of the 

INLET BOX ASSEMBLY.

The 

INLET BOX TOP

 should fit over the whole assembly

.Screw the 

INLET BOX C CHANNEL SUPPORT (D01-

0859)

 to the 

INLET BOX FRONT PANELS

.  There are (2)

C-CHANNELS

 per 

FRONT PANEL

.  Attach the 

INLET

BOX WINDOW SILL C CHANNELS (D01-0782 & D01-
0783)

 around the square holes on the 

INLET BOX FRONT

PANELS 

along with the 

AIR ACCESS DOOR FRAME

ANGLES (D01-0395 & D01-0396) and OPERATOR’S
DOOR HINGE BRACKET (D31-0161).

Screw the 

PERFORATED AIR ACCESS DOOR PANEL

(D01-0781) 

& the 

PERFORATED SIDE DUCT PANEL

(D01-0780)

 to the inside of the 

FRONT PANELS.

Place the 

INLET BOX FLASHING (D01-0860, Figure 1)

over the dryer hitch and bolt it to the 

INLET BOX DECK

PLATES.

Walkway Door Assembly

The 

WALKWAY DOOR ASSEMBLY

 is the same for both

doors except that one door mounts upside down from the
other.  The hinge holes show the difference in mounting.
Mount the 

INLET WALKWAY DOOR TOP/BOTTOM

FRAME ANGLE (D01-0575, Figure 2)

 to the top and bot-

tom of the large hole in the 

INLET ENTRY PANEL

.  There

are two angles on each door.
Mount the

 INLET WALKWAY DOOR SIDE FRAME

ANGLE (D01-0576, Figure 2)

 to each side of the large

hole in the 

INLET ENTRY PANEL

.  There are two angles

on each door.
Mount the 

WALKWAY DOOR HINGE—HR SEGMENT

(D01-0595, Figure 2)

 to the 

INLET ENTRY PANEL.

Mount the 

WALKWAY DOOR CATCH ANGLE (D01-0597,

Figure 2)

 to the 

INLET ENTRY PANEL

 with the angle

pointing to the center of the door hole.
Mount the 

WALKWAY DOOR HINGE—DOOR SEG-

MENT (D01-0596, Figure 2),  STANDOFF BRACKET
(D01-0548, Figure 2), 2 MOUNTING BRACKETS (D01-
0549, Figure 2), 

and the

 POWER BOX DOOR LATCH

MECHANISM (D01-0547) 

to each of the

 WALKWAY

DOORS (D01-0574, Figure 2)

.

Mount the 

WALKWAY DOORS

 to the 

INLET ENTRY

PANELS

.

Side Duct Assembly

The 

SIDE DUCT ASSEMBLY

 can be completed on the

ground or in place on the dryer.  Assemble the 

SIDE

DUCT CORNER

 by bolting the 

SIDE DUCT FRONT COR-

NER (D01-0562, Figure 4), SIDE DUCT BACK CORNER
(D01-0563, Figure 3), SIDE DUCT CORNER TOP (D51-
0219 RH, D51-0220 LH, Figure 4), SIDE  DUCT  COR-
NER  BOTTOM (D51-0217 RH, D51-0218 LH, Figure 3)

,

and three 

SIDE DUCT PANELS (D01-0561,    Figure 3)

together with the flanges out and (4) 

INNER SUPPORT

ANGLES (D01-0632)

. at each vertical seam on the heat

reclaimer. Assemble the 

TRANSITION DUCT

 by bolting

the 

SIDE DUCT TOP  (D51-0213, Figure 4), SIDE DUCT

BOTTOM (D01-0564, Figure 3)

, and four 

SIDE DUCT

PANELS (D01-0561, Figure 4)

 together with the flanges out.

Keep the bolts on this assembly loose, so that it can be
pulled into place later on.  In this assembly the tops fit
over the side panels, and the side panels fit over the bot-
tom panels.

Transition Column Assembly

The 

TRANSITION COLUMN ASSEMBLY

 is attached to

the left and right

Содержание Airstream PNEG-362 2000 Series

Страница 1: ... 9 9 7 1 9 9 7 1 9 9 7 1 9 9 7 1 9 9 7 HEAT RECLAIMER A S S E M B L Y I N S T R U C T I O N S PNEG 362 2000 SERIES TWO MODULE DRYER MODELS A I R S T R E A M G R A I N C O N D I T I O N I N G S Y S T E M S ...

Страница 2: ...2 ...

Страница 3: ... Heat Reclaimer Platform Installation 5 Bracing Of Assemblies 5 Inlet Box Assembly 5 Walkway Door Assembly 6 Side Duct Assembly 7 Transition Column Assembly 7 Column Assembly 8 Air Access Door Assembly 8 Decals 8 HEAT RECLAIMERASSEMBLYINSTRUCTIONS TABLE OF CONTENTS ...

Страница 4: ...ODIFICATIONS TO THE PRODUCT NOT SPECIFICALLY COVERED BY THE CONTENTS OF THIS MANUAL WILL NULLIFY ANY PRODUCT WAR RANTY THAT MIGHT HAVE BEEN OTHERWISE AVAILABLE THE FOREGOING WARRANTY SHALL NOT COVER PRODUCTS OR PARTS WHICH HAVE BEEN DAMAGED BY NEGLIGENT USE MISUSE ALTERATION OR ACCIDENT THIS WARRANTY COVERS ONLY PRODUCTS MANUFACTURED BY GSI THIS WARRANTY IS EXCLUSIVE AND IN LIEU OF ALL OTHER WARRA...

Страница 5: ...OTTOM OUTER TOE BOARDS D01 0644 D01 0645 Install the PLATFORM SUPPORT BEAM D01 0591 Figure 1 to the SERVICE PLATFORM FRAMEWORK Install the INLET BOX DECK PLATE D01 0571 Figure 1 to the SERVICE PLATFORM FRAMEWORK using the ex isting corner bolts Drill a 3 8 diameter hole for every hole around the outer edge of the INLET BOX DECK PLATE Place a 5 16 WHIZ BOLT AND NUT into each of these holes to secur...

Страница 6: ... same for both doors except that one door mounts upside down from the other The hinge holes show the difference in mounting Mount the INLET WALKWAY DOOR TOP BOTTOM FRAME ANGLE D01 0575 Figure 2 to the top and bot tom of the large hole in the INLET ENTRY PANEL There are two angles on each door Mount the INLET WALKWAY DOOR SIDE FRAME ANGLE D01 0576 Figure 2 to each side of the large hole in the INLE...

Страница 7: ...7 HEAT RECLAIMERASSEMBLYINSTRUCTIONS Figure 1b Inlet Box Assembly Noise Suppressor Panel Installation Figure 1a Inlet Box Assembly ...

Страница 8: ...re 3 to the bottom of the TRANSITION REAREND COVER TRANSITION VENT PANEL and the corre sponding vertical joint of the dryer column Bolt one TRANSITION FRONTEND COVER to the SIDE DUCT BOTTOM first COLUMN BUTTRESS VENT PANEL and to the first column joint Bolt the TRANSITION COLUMN ROOF PANEL D01 0631 Figure 3 to the top of the TRANSITION COLUMN PANELS Mount the RH SMALL MEDIUM AND LARGE TRAN SITION ...

Страница 9: ...sing the 5 16 BOLTS and LOCKNUTS S 4276 S 5220 Assemble the LINKAGE MECHANISM BLK 10049 D15 0156 D51 0157 D51 0158 D51 0159 D51 0165 S 4318 according to the drawings number Figure 6 Drill a 0 75 hole in the INLET BOX DECK PLATE to allow the chain to pass and be located for easy access and away from the lower fan inlets Decals The DECALS D01 0614 should be mounted on the front of the TRANSITION REA...

Страница 10: ...10 HEAT RECLAIMERASSEMBLYINSTRUCTIONS Figure 3a 2012 and 2014 Outside Side Duct Assembly ...

Страница 11: ...11 HEAT RECLAIMERASSEMBLYINSTRUCTIONS Figure 3b 2018 and 2020 Outside Side Duct Assembly ...

Страница 12: ...12 HEAT RECLAIMERASSEMBLYINSTRUCTIONS Figure 3c 2022 and 2026 Outside Side Duct Assembly ...

Страница 13: ...13 HEAT RECLAIMERASSEMBLYINSTRUCTIONS Figure 4a 2012 and 2014 Inside Side Duct Assembly ...

Страница 14: ...14 HEAT RECLAIMERASSEMBLYINSTRUCTIONS Figure 4b 2018 and 2020 Inside Side Duct Assembly ...

Страница 15: ...15 HEAT RECLAIMERASSEMBLYINSTRUCTIONS Figure 4c 2022 and 2026 Inside Side Duct Assembly ...

Страница 16: ...16 HEAT RECLAIMERASSEMBLYINSTRUCTIONS Figure 5 Column Panel Assembly ...

Страница 17: ...17 HEAT RECLAIMERASSEMBLYINSTRUCTIONS Figure 6 Air Access Door Assembly ...

Страница 18: ...18 A I R S T R E A M G R A I N C O N D I T I O N I N G S Y S T E M S 1004 E Illinois St Box 20 Assumption IL 62510 0020 phone 217 226 4421 fax 217 226 4498 May 1997 ...

Отзывы: