Install Upper Handrails
IMPORTANT:
For safety purposes, make sure head of bolts is to the inside of platform with nuts on
outside at all connections.
NOTE:
Upper handrails do not require any cutting prior to installation.
1. Attach two (2) 25.6" in length middle drive handrails (HP1624HMD) along Deck E and the lower head.
These are the two (2) shortest sections of upper handrail. Connect using 5/16" nuts (S-10268) and
5/16" x 2" bolts (S-7877). Torque to standard specifications.
2. Attach four (4) hatch handrails (HP1648HHS): one on each side of the middle drive at each end of
the platform. Handrails will fit without adjustment. Connect using 5/16" nut (S-10268) and 5/16" x 2"
bolts (S-7877). Torque to standard specifications.
3. Two (2) 59.183" far hatch handrails (HP1624HFH) and two (2) 54.65" handrails (HP1624HNH) opposite
each other along Deck A and Deck C using 5/16" x 2" bolts (S-7877) and 5/16" nuts (S-10268).
Figure 8U Top Rails
Ref #
Part #
Description
A
HP1624HFH
59.183" Far Hatch Handrail
B
HP1648HLH
36.895" Hatch Handrail
C
HP1648HMD
26.7" Middle Drive Handrail
D
HP1624HNH
54.65" Near Hatch
E
S-7877
5/16" x 2" Bolt
F
S-10268
5/16" Flange Nut
Top Rails