2. Component Installation
10
PNEG-1405
Moisture Controller
Figure 2I Grey flex conduit routing
7. Connect another 90° conduit connector to the other end of the grey flex conduit and connect that to
the white junction box on the leg gusset as shown in the
Figure 2I
, then feed the shielded wire down
the EMT conduit forward to the “T” junction box. Then feed shielded wire through the black flex
conduit and connect conduit to the Moisture Manager control box.
8. To mount the plenum thermocouple, knock out one of the prepunched wholes in either the front or
rear column end panels. Be sure to knock out a hole for the plenum and not the grain column.
Figure 2J
Figure 2K Plenum Thermocouple (602E181)
Where to install the Plenum Thermocouple. The
Figure 2J and
Figure 2K
is showing the right rear side of
the dryer (near the rear access door).
Ref #
Description
D
Secure conduit with conduit clamp here
D
Ref #
Description
E
Plenum knockout holes
E