113466_67_68HBC   Revision date: 08.27.19

2

Assemble Frame

FRAME ASSEMBLY

Use the diagrams and information that follows to assemble 

the main frame.

ATTENTION:

 Rafters are heavy. 

Move rafter with assistance or using a small lift to prevent damage and injury.

 Determine best way to move rafters into 

position and to set them onto each set of ground posts. 

Do not set rafters into position until ground post concrete has set (if applicable). 

Gather parts:
•  Assembled rafters, 102856 end clamps, & 102548 cross connectors
•  FAG336B (5/16” x 2-1/2”) bolts & FALB02B (5/16”) nuts
•  1.315" Pipe: 131S075 & 131P0xxx (where x represent length of last pipe)

Complete these steps:
1.  Slide one end clamp (102856) onto each end of a rafter as shown in detail 

above and in Quick Start diagrams.

2.  Set first end rafter in place and anchor to ground posts using 5/16" bolts 

and nuts. Add braces for support if needed or have an assistant hold until 

next rafter is added and connected with purlins.

3.  Set next rafter in place and secure using 5/16" bolts and nuts. 

 

ATTENTION:

 Only the two end rafters use 102856 end clamps as shown. 

All interior rafters use 102548 cross connectors to secure purlins to rafters. 

See details in Quick Start section for additional diagrams.

4.  Using side profile diagram in Quick Start section for your building length, 

attach first purlin pipe on each side between the two rafters. 

Do not 

tighten clamps at this time.

5.  Add next rafter and connect using next purlin pipe. See side profile 

diagram for pipe identification. 

 

NOTE:

 Set purlin height on each side just below rafter bend as shown in 

diagrams. Purlin runs should be at same location on each side of frame. 

For accuracy, stretch a string line end-to-end to keep purlins aligned. See 

diagram above.

6.  Check on-center spacing of rafters before clamps are tightened.
7.  Using a long level or the string line (if present), ensure purlin pipes are 

level and tighten cross connectors and end clamps.

Ground Level

String Line

Level

Step 1

Содержание 113466H B

Страница 1: ...ved Reproduction is prohibited without permission STK DIMENSIONS 113466H B C 26 W x 5 H x 24 L 113467H B C 26 W x 5 H x 36 L 113468H B C 26 W x 5 H x 48 L Actual building design and dimensions may dif...

Страница 2: ...chor assembly is an integral part of the high tunnel construction Improper anchoring may cause tunnel instability Failing to anchor tunnel properly may void manufacturer s warranty and may cause serio...

Страница 3: ...concrete continue with next procedure 12 Install tighten and secure end panels 13 Install tighten and secure main cover 14 Read care and maintenance information 15 Complete and return all warranty in...

Страница 4: ...not allow cover to remain open for extended time Periodically unroll cover for cleaning and to allow it to dry Remove debris and objects that accumulate on cover Use tools that will not damage cover w...

Страница 5: ...ort Lock FA4110 FA4115 Hook Loop Fasteners FA4110 FA4115 102856 End Clamp 102197 Aluminum U Channel Film Cover only 104642 A Angle Bracket 102198 Spring for Aluminum U Channel Film Cover only 102548 C...

Страница 6: ...of frame is measured from center to center of ground posts 2 After placing first corner stake string a line the frame width center to center of ground posts and drive second corner stake 3 String a l...

Страница 7: ...ring frame as described in the MUST READ document do not auger holes for ground posts Instead follow the steps to mark ground post locations and drive posts into the ground at those locations See info...

Страница 8: ...ts in place See diagram below All posts to be plumb before adding concrete Use mounting holes in posts and customer supplied fasteners and stakes to hold posts in place 3 Add concrete to anchor posts...

Страница 9: ...Wrap screws and slices with duct tape Gather parts Rafter pipes LPT166ES1W26 LPT166PS1W26 166S051 166S063 FA4472B Tek screws 100442 magnetic nut setter Duct tape STEP 1 Select rafter pipes to assembl...

Страница 10: ...n assistant hold until next rafter is added and connected with purlins 3 Set next rafter in place and secure using 5 16 bolts and nuts ATTENTION Only the two end rafters use 102856 end clamps as shown...

Страница 11: ...art section for additional information and pipe identification Purlin runs end to end down center at top of each rafter ATTENTION At this time do not install brackets that secure square peak purlin to...

Страница 12: ...f cover is shown rolled to peak Cover is installed later 2 Assemble end panel conduit using the 1 315 pipe noted above secure each pipe joint with Tek screw and tape over screw Slide conduit into pock...

Страница 13: ...of end panel Attach each end of conduit to ground post using Tek screws and QH1330 brackets 3 Measure between end rafter ground posts to determine final conduit length Cut assembled conduit to fit if...

Страница 14: ...as needed so zippers function properly then continue 10 Drive a Tek screw through each clip and into rafter Position screws in a location that will not contact cover material Tape over screw if neede...

Страница 15: ...alternative steps for installation On the outside of frame attach first baseboard ground post using two 2 5 16 carriage bolts and nuts Countersink bolt heads if carriage bolts are not used Continue a...

Страница 16: ...ION 115287 Gather parts 115287 curtain stabilizer bars GS0049 splice plate FA4472B Tek screws 100442 magnetic nut setter 5 115287 115287 Side Views with baseboard without baseboard Tab Install bar as...

Страница 17: ...dditional information 2 Assemble 1 315 roll up conduits one for each side See side profile diagrams in Quick Start section for details and pipe identification NOTE Secure each pipe splice with a Tek s...

Страница 18: ...below for frame cover material Solid Black Silver Cover B Diagrams show attaching aluminum bar 110155 through cover and into peak purlin of frame Install Tek screws approximately 17 on center through...

Страница 19: ...ame after removing excess material Check cover length NOTE Once cover is wrapped around conduit conduit should rest on ground next to frame when length is correct See photo inset right 3 Unroll cover...

Страница 20: ...to 36 extension pipe using one 1 Tek screw 2 Slide 6 easy spin pipe 166P006 onto free end of 36 extension pipe 3 Attach universal joint to end of 36 extension pipe 4 Attach assembly to roll up cover...

Страница 21: ...sive 7 Repeat Steps 3 6 to apply hook hoop fastener in all remaining locations on frame 8 Beginning with one side roll cover down to stabilizer bar and lock cover into place 9 Verify cover is position...

Страница 22: ...12 from rafter splice Positon B Approx 36 from top center of rafter Positions C Mid point between A B GROUND LEVEL X X X X X X X Length 48 GROUND LEVEL X X X X Length 24 GROUND LEVEL X X X X X X Leng...

Страница 23: ...Repeat as cover rolls down tunnel frame End fasteners can be reached when cover is locked down Film is shown Actual cover may differ ATTENTION Never leave cover partially open Cover must be fully ope...

Страница 24: ...Guide GrowSpan Roll Up Low Pro Tunnel 26 Wide Frame ATTENTION Diagram shows optional baseboard installed below stabilizer bar If baseboard is not used install stabilizer bar at ground level Ground Le...

Страница 25: ...9 25 11 1 2 CENTER TO CENTER OF GROUND POSTS 2 0 EMBEDMENT 2 5 1 8 12 1 7 8 1 4 3 8 5 5 15 16 GROUND LEVEL TO STRUCTURE PEAK GROUND LEVEL ATTENTION Diagram shows optional baseboard installed below sta...

Страница 26: ...ND POST 102675 RAFTER LPT166ES1W26 RAFTER LPT166ES1W26 RAFTER LPT166PS1W26 RAFTER 166S063 RAFTER 166S063 RAFTER 166S051 RAFTER 166S051 ALUMINUM BAR 110155 IF APPLICABLE PURLIN BRACKET END 102856 MID 1...

Страница 27: ...ar If baseboard is not used install stabilizer bar at ground level 4 0 RAFTER SPACING 24 0 CENTER TO CENTER OF GROUND POSTS 2 0 EMBEDMENT GROUND LEVEL SIDEWALL PURLIN SIDEWALL PURLIN ROLLUP CONDUIT 13...

Страница 28: ...ROUND LEVEL SIDEWALL PURLIN PEAK PURLIN STABILIZER BAR 131S075 5 131P0735 1 PEAK PURLIN 102897 4 S15P048 1 STABILIZER BAR SIDEWALL PURLIN ROLLUP CONDUIT 115287 3 CUSTOMER SUPPLIED BASEBOARD OPTIONAL A...

Страница 29: ...ar If baseboard is not used install stabilizer bar at ground level 4 0 RAFTER SPACING 48 0 CENTER TO CENTER OF GROUND POSTS 2 0 EMBEDMENT GROUND LEVEL SIDEWALL PURLIN PEAK PURLIN STABILIZER BAR 131S07...

Страница 30: ...30 113466_67_68HBC Revision date 08 27 19 Connections VIEW 7 VIEW 8 CONNECTION ATTENTION Optional baseboard not shown...

Страница 31: ...VIEW 3 VIEW 2 VIEW 4 VIEW 6 VIEW 7 NOTE VIEW 8 VIEW 5 VIEW 9 VIEW 1 5X 14 X 1 TEK SCREW SPLICE PLATE GS0049 STABILIZER BAR STABILIZER BAR RAFTER 2X 12 X 1 TEK SCREW GROUND POST STABILIZER BAR install...

Страница 32: ...PLODED VIEW 2X 12 X 1 TEK SCREW EVERY 17 ALUMINUM BAR 110155 BLACKOUT MATERIAL PURLIN 1 5 SQ BLACKOUT MATERIAL CONNECTION PEAK IF APPLICABLE CLEAR FILM CONNECTION PEAK IF APPLICABLE NOTE BLACKOUT COVE...

Страница 33: ...ce Photo above shows frame with film cover Cross connectors secure side purlin to rafters Stabilizer bar is shown secured to outside of frame and runs near ground level the full length of the frame Th...

Отзывы: