Connect two batteries with Network Cable B, and connect battery and PCS with Network Cable A. 
Insert one plug into the Link-In of Battery 1 and other plug into the Link-Out of Battery 2.

.

Network Cable A
to PCS 
Network 
Port

Plug 2

Network 
Cable B

Battery 1

Battery 2

.

Plug 1

Two plugs (shown as plug1 and plug 2) are exactly 
the same and can be mixed.
If the voltage difference is measured more than 
1V, the difference shall be adjusted to be no more 
than 1V either by charging the battery with lower 
voltage or discharging the battery with higher 
voltage before conducting the parallel connected 
installation;
Please press the POWER button of any battery to 
turn on/off  system under parallel connection.

!

CAUTION 

5  Power on/off Battery

* 

Technical knowledge is involved in the electrification process, and electricians must go 

               through technical training and obtain certificates in compliance with local law and regulations.
* 

Please stand on dry insulating objects and do not wear metal objects such as watches, 

               necklaces and rings during operation. Insulating tools should be used.
* 

Do not contact with two charged positions with potential difference.

* 

Make sure that the PCS is turned off before checking battery. 

!

CAUTION 

Network Cable B

Network Cable A is defined as the cable connecting PCS and Battery 1, Network Cable B as the 
cable connecting two batteries. Two cables are made based on the pin difinition as shown in 
Section 3. The other end of Network Cable A will be made according to the PCS specifications.
Two plug are used to define master battery and slave batteries.  

Network Cable A

Network Cable B

Plug

4. Insert network cables

Shenzhen Growatt New Energy Technology CO.,LTD

.

Содержание GBLI6532

Страница 1: ...GBLI6532 Battery System Quick Installation Guidance ...

Страница 2: ...mpliance with storage transportation installation and usage requirements specified in Quick Guidance and Manual are not coved by Warranty CAUTION 1 Product Overview LED 1 LED 2 LED 4 LED 5 LED 3 2 1 3 4 5 6 7 8 1 475 765 150 148 745 No label Name No label Name 1 POWER Power button 5 Link out Parallel Network Output 2 Positive terminal 6 Grounding terminal 3 _ Nagative terminal 7 PCS Network port t...

Страница 3: ...or use battery near explosive or inflammable substances Use battery in well ventilated environment with temperature ranging from 10 to 50 For outdoor installation build sun rain shade to avoid direct sunlight and rain exposure Do not place battery upside down nor alongside as the above picture shown Maintain a minimum level of dust and dirt in the environment CAUTION 2 θ 5 θ 5 Wall Wall Wall Groun...

Страница 4: ... drilling spots Note 1 Keep a minimal distance of 320mm between wall and bracket a maximum distance of 765mm between bracket and ground Leave a minimum clearance of 133mm before the front surface of battery 2 The weight capacity of wall should exceed 4 times weight of batteries 3 At least two persons conduct the installation One person places the bracket on wall and ensure the gradienter horizonta...

Страница 5: ...urface of battery Step 2 Drill in the spots for at least 60mm Clean the soil and drive expansion tube into hole 4 Drive M8 screw through notch of latch into wall Step 3 Fix battery on bracket from the top down Note In order to guarantee a stable connect between battery and bracket please visually check if the two upper joints are fixed Try to move the lower part of battery away from wall The conne...

Страница 6: ...6 GND ISO 7 GND ISO 8 WKP OUT 3 1 Connect Cables for Single Battery 1 Measure battery voltage with a multi meter and ensure the voltage output is 0V under power off mode 2 Fasten grounding terminal and grounding cable with M6 screw recommending a torque of 5N m 3 Insert power cables into DC Breaker and battery terminals orange positive cable and black negative cable Plug one end of Network Cable A...

Страница 7: ...ERTER 300 d 500 300 d 500 6 2 Fasten ground terminal and grounding cable with M6 screw for two batteries 3 Insert power cables Plug one end of power cables into DC breaker Measure the positive and negative terminal blocks of each battery with a multi meter and ensure the voltage outputs under off mode are all 0V After that plug the other end of power cables into battery terminals to PCS Positive T...

Страница 8: ...hnical knowledge is involved in the electrification process and electricians must go through technical training and obtain certificates in compliance with local law and regulations Please stand on dry insulating objects and do not wear metal objects such as watches necklaces and rings during operation Insulating tools should be used Do not contact with two charged positions with potential differen...

Страница 9: ...us PCS HMI screen indicates normal PV or mains supply input Single Battery Power on battery by pressing POWER button Power on battery by Activating PCS Procedures Acceptation criteria Procedures Acceptation criteria 1 Close the breaker from battery to converter Breaker in ON status 1 Close the breaker from battery to converter Breaker in ON status 2 Press POWER button for two seconds and observe t...

Страница 10: ...Address No 28 Guangming Road Shiyan Street Bao an District Shenzhen P R China Press the POWER button of any battery for two seconds Five LED lights will flicker for three times and battery turns off Battery will turn off 25 minutes after Network Cable A connection between PCS and PACK fails 5 2 Power off Battery ...

Отзывы: