A.5 Operation

Module continuously monitors boiler water temperature and 

fires or shuts off burner based on this temperature data.

1. 

When “Call for Heat” occurs, control enables circulator 

and monitors boiler water temperature to determine 

whether thermostat can be satisfied without firing 

burners.  

Table 6  - Operation State Codes

State 

Code 

Number

Definition

Explanation

1

Idle

or

Circulator

Standby - no call for heat
Heat request present. Boiler temperature sufficiently high to run circulator pump 

only.

4

Pre-purge

System is purging before ignition trial; includes Pilot Valve circuit diagnostics.

6

Spark

System sparking.  Flame is not present.

7

Flame stabilization

Flame signal is being established.  Variation in signal is allowed during this state, 

flame must be stable at end of period

8

Running

System is running.  Flame signal must be present.

9

Post-Purge

System is purging at end of call for heat

10

Retry Recycle Delay

Successful ignition was not detected, and delay is called before retry.
Flame signal was lost during state 7 or 8, and delay is called before retry (32 

second delay)

13

Soft lock-out

Soft lockout duration is one hour, may override with manual reset.

14

Hard lock-out

Manual reset is required for hard lockout

15

Wait for limit to close

Possible thermostat call for heat; limit switch is open.

16

Flame out of sequence

Flame signal sensed before trial for ignition.  Appropriate alarm is sent. 

OR

Flame signal sensed out of sequence during post purge.  Appropriate alarm is 

sent.                       OR

Flame signal present when not expected.  Appropriate alarm is sent.

17

Pilot valve diagnostics

Pilot valve circuitry diagnostics during pre-purge.

Current leakage detection Self check performed at start up, again at beginning of heat cycle, and during 

“Wait for Recovery “ State.

Wait for recovery

Self check performed at start up, again at beginning of heat cycle, and during 

“Wait for Recovery “ State

18

Wait for damper to open

Control has signaled damper/pressure switch 

to close, and is waiting for completion.                                                                                                     

If damper/pressure switch does not close within 60 seconds, control goes to 

State 20.

19

Wait for damper to close

Damper is closed and control waits for damper to open. 

Checked at beginning of heat cycle before opening damper.                                                                   

If damper does not open in 60 seconds, control goes to State 21.

20

Wait for damper to open            

(Failed close)

Damper has not opened (end switch not closed) at beginning of heat cycle.   

Alarm message is sent, control is NOT in lockout.

21

Wait for damper to close              

(Failed open)

Damper has not closed despite actuator de-energized.                                 

Alarm message is sent, control is NOT in lockout.

2. 

Control determines burner operation is required, 

module proceeds to start burner (see state codes list) 

and heats water in boiler until setpoint temperature is 

achieved or thermostat is satisfied. . 

3. 

Burner is de-activated, ignition module completes 

heating cycle, returns to idle and waits for temperature 

to drop again. 

4. 

Circulator is turned on throughout “Call for Heat.”

 P/N# 240011109, Rev. C [07/22/2015]

Содержание GMGW Series

Страница 1: ...N OPERATIONS AND MAINTENANCE MANUAL Manufactured by ECR International Inc 2201 Dwyer Avenue Utica NY 13501 web site www ecrinternational com Models GMGWB045FE GMGWB120FE GMGWB070FE GMGWB145FE GMGWB096...

Страница 2: ...a level to 2 000 ft 610m above sea level United States over 2000 ft 610m above sea level Reduce input rate 4 for every 1 000 ft 304m above sea level 2 Net AHRI Water Ratings shown based on piping and...

Страница 3: ...1 GMGWB070FE 15 7 5 28 2015 16 415 16 1 GMGWB096FE 15 7 5 28 2015 16 415 16 1 GMGWB120FE 19 9 6 29 217 16 57 16 1 GMGWB145FE 19 9 6 29 217 16 57 16 1 GMGWB170FE 22 113 16 7 30 2115 16 515 16 1 GMGWB19...

Страница 4: ...agram 18 12 Lighting Instructions 20 13 Normal Sequence Of Operation 21 14 General Instructions 21 15 Checking Gas Input Rate To Boiler 23 Appendix A Control Module 24 A 1 Installation Environment Con...

Страница 5: ...NCE WARNING Keep boiler area clear and free from combustible materials gasoline and other flammable vapors and liquids DO NOT obstruct air openings to the boiler room Modification substitution or elim...

Страница 6: ...and service circulator replacement condensate trap control replacement etc 6 Locate boiler on level solid base as near chimney as possible and centrally located with respect to heat distribution syste...

Страница 7: ...filtration rate is less than 0 40 air changes per hour See Table 3 for space with boiler only Use equation for multiple appliances Volume 50 ft3 x Total Input Mbh Known Air Infiltration Rate See Table...

Страница 8: ...ater than that of the relief valve outlet over the entire length of discharge line have no intervening shutoff valve between safety relief valve and discharge to atmosphere do not plug or place any ob...

Страница 9: ...relief valve Systems with automatic fill valves require back flow prevention device Install discharge piping from safety relief valve See Warning Page 8 When boiler is connected to heating system util...

Страница 10: ...T CIRCULATOR A PRESSURE REDUCING VALVE PROPER BACKFLOW PROTECTION DEVICE GATE VALVE PURGE VALVE NOTICE Circulators in following illustrations are mounted on system supply side mounting on system retur...

Страница 11: ...s Page 9 5 CONNECTING SUPPLY AND RETURN PIPING Figure 3 Bypass Piping Automatic Mixing Valve See Bypass Piping Options Page 9 BOILER WATER INLET ALTERNATE CIRCULATOR LOCATION TO SYSTEM FROM SYSTEM CIR...

Страница 12: ...12 5 CONNECTING SUPPLY AND RETURN PIPING Figure 5 Single Zone System With DHW Priority Figure 6 Multi Zone System with Circulators and DHW Priority P N 240011109 Rev C 07 22 2015...

Страница 13: ...NG SUPPLY AND RETURN PIPING Figure 7 Multi zone System With Zone Valves And DHW Priority With Circulator Figure 8 Multi zone System With Zone Valves And DHW Priority With Zone Valve P N 240011109 Rev...

Страница 14: ...ion of the common venting system the common venting system should be re sized to approach the minimum size determined using the appropriate tables in Chapter 13 of the National Fuel Gas Code ANSI Z223...

Страница 15: ...e in visible location following installation 5 Thermostat s heat anticipator must be adjusted to match total current draw of all controls associated with boiler during heating cycle 8 VENT DAMPER INST...

Страница 16: ...ing with hooks straps bands brackets hangers or building structure components to prevent or dampen excessive vibrations and prevent strain on gas connection Boiler will not support piping weight Use t...

Страница 17: ...connection 4 Line power connections 5 LWCO kit 550002998 includes wiring instructions and wiring diagrams If using a different LWCO refer to the specific instructions provided with that unit See wiri...

Страница 18: ...2 Integrated High Limit Electronic Ignition Control WARNING Modification substitution or elimination of factory equipped supplied or specified components may result in personal injury or loss of life...

Страница 19: ...19 11 WIRING DIAGRAM Figure 13 Integrated High Limit Electronic Ignition Control P N 240011109 Rev C 07 22 2015...

Страница 20: ...ff Gas To Appliance and call qualified service technician or your gas supplier TO TURN OFF GAS TO THE APPLIANCE 1 Set the thermostat to lowest setting 2 Turn off all electric power to the appliance if...

Страница 21: ...ave them repaired immediately Check and maintain circulators Refer to circulator manufacturer s instructions Inspect venting system at the start of each heating season Check vent pipe from boiler to c...

Страница 22: ...ns of corrosion rust or scale buildup Area around boiler must be kept clear and free of combustible materials gasoline and other flammable vapors and liquids Free flow of combustion and ventilating ai...

Страница 23: ...ter column from specified pressure Primary air adjustment is not necessary therefore air shutters are not furnished as standard equipment Air shutters can be furnished on request where required by loc...

Страница 24: ...loose Refer to enclosed addendum for wiring instructions when using indirect hot water heater Verify vent damper connection is made See page 15 A 3 Adjusting Settings To discourage unauthorized changi...

Страница 25: ...n Appropriate alarm is sent OR Flame signal sensed out of sequence during post purge Appropriate alarm is sent OR Flame signal present when not expected Appropriate alarm is sent 17 Pilot valve diagno...

Страница 26: ...set at thermostat Check for correct installation and wiring before replacing any component Control module cannot be repaired If it malfunctions it must be replaced Use only qualified service agent to...

Страница 27: ...ppears 63 Soft lockout maximum number of recycles exceeded After main burner ignition Soft lockout 64 Soft Lockout electronics failure On board self diagnostics detected error Soft lockout 65 Over tem...

Страница 28: ...ck for cracked ceramic insulator which can cause short to ground and replace igniter sensor if necessary At gas valve disconnect main valve wire from MV terminal Turn on power and set thermostat to ca...

Страница 29: ...29 NOTES P N 240011109 Rev C 07 22 2015...

Страница 30: ...30 NOTES P N 240011109 Rev C 07 22 2015...

Страница 31: ...31 Company Address Phone Company Name Tech Initials Service Performed Date SERVICE RECORD P N 240011109 Rev C 07 22 2015...

Страница 32: ...ture is equipped with an override which is provided primarily to permit the use of an external energy management system that serves the same function THIS OVERRIDE MUST NOT BE USED UNLESS AT LEAST ONE...

Отзывы: